LNG

Vice President, LLoyds Energy, LNG

START Date

Lloyds Energy, Vice President Project Services, Global FLNG Projects, London, Dubai & Moscow​
• A $15b multiple vessels, near shore LNG project designed as a generic concept with potentially global applications.
• As a new start operator I started the project controls function, recruiting a small team and commenced the creation of the master control schedule and control estimate as well as establishing company policy and procedures for project management, control and governance.

GENERAL MANAGER OF PROJECT CONTROL DIVISION, IKPT - TOYO, LNG, Gas Processing, Fertilizer

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
2000

Major Project Experience (18.5 years experience)

· Coal Boiler Project & Ammonia Urea (Pupuk Kaltim, Indonesia), Sep 2011 - Now

· Ammonia ura Collie Phase1 – Project Development Phase (Perdaman Chemicals & Fertilizers Pty. Ltd, Perth, West Australia), Sep.2009 – Jan. 2011

· Qatar 3LLNG (QGX, RGX, QCS), Rass Laffan – QPG, and AKG2 LNG (Chiyoda Corp, Yokohama, Japan), Mar 2007 – Mar 2008

· South Sumatera Gas Development (Pertamina EP, Indonesia), June 2004 – Nov. 2006

Senior Planning Engr, TECHNIP MIDDLE EAST QATAR, LNG,RAS LAFFAN QATAR

START Date
END Date

-To know about the scope of a project and how its being planned.
-Provide regular key information to management reporting on schedule.
-Review scope change request for the impact on schedule and critical path of the project.
-To develop and manage a centralized planning and control system for the overall production Project portfolio that will facilitate project delivery within established targets.
-Provide monthly progress updates, forecast completion together with the critical path and trend analysis.

  • Implementation of Primavera v6.0 and Microsoft Project plannin