Construction Project Control Manager, Vial y vives-DSD, Kelar
START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1500
Experience Hours (Forensic Analysis)
1500
This was the first power plant in Chile with combined cycle technology the Project name is Kelar Plant, this plant reuses 100% of seawater. The project investment of $600 Million (USD), main works: installation 2 gas turbines of 350 Ton, 1 steam turbine 250 Ton, 1500 tons of steel structures, 180,000 m3 of concrete, 1,200,000 m3 of earthworks, 2,500 tons of reinforcement bars, water & waste treatment plant, several diesel storage tanks, installation of cooling tower 200 meters of length and other major works.