Ganshu Jinchang 300MW thermal plant Boiler Project

Lead Planner, Alstom China - Wuhan Boiler Company Ltd., Luneng Xinjiang Hebukesaier Thermal Power Plant 2*300MW Boiler Project,Guo Dian Xi’an Weiyang Thermal Power Plant 2*350MW SC Boiler Project,Morocco SAFI 660MW SC Boiler Island Project,Ganshu Jinchang

G
Ganyi WANG 👤 Member for 15 years 2 months
START Date

Responsibilities:

  • Lead and mentor the Project Planners.
  • Support Tendering department to set up the Tendering Time Schedule.
  • Review schedule information from Engineering, Sourcing and Manufacturing departments.
  • Review the relevant departments’ Resource Plan.
  • Develop and optimize overall Project Master Time Schedule (Baseline) to meet all contract requirements which include milestone dates, payment dates and other requirements.
  • Regularly Monitor.