Aromatics Plant

Planning & Project Control Coordinator, PIDEC, 2nd Urea and Ammonia Pardis Petrochemical, Aromatics Plant,MTBE Project

START Date
END Date
Experience Hours (Planning & Scheduling)
11400
Experience Hours (Cost Management)
1350

2003 ~ 2006

PARDIS Ammonia and Urea Project No.2

 

EP contract (Engineering, Procurement)

Applicant: Iran National Petrochemical Company

Contractor: Consortium of Toyo, Chiyoda & PIDEC

Position: Engineering planner and project controller

 

Key Responsibilities:

Principal Piping Design/piping Supervisor, Thechnip, Aromatics Plant, La cangrejera Veracruz, Mexico, PEMEX

START Date
END Date

I'm a Piping Designer, I have 34 years of experience in development of Chemical and Petrochemical projects. I live in Monterrey, Mexico. The last projects I have developed in Technip-Monterrey/Houston and KBR Monterrey/Houston (10 years)

And Ihave 11 years of experience with PDS, Smart Plan.

Principal Piping Design/piping Supervisor, Thechnip, Aromatics Plant, La cangrejera Veracruz, Mexico, PEMEX

START Date
END Date

I'm a Piping Designer, I have 34 years of experience in development of Chemical and Petrochemical projects. I live in Monterrey, Mexico. The last projects I have developed in Technip-Monterrey/Houston and KBR Monterrey/Houston (10 years)

And Ihave 11 years of experience with PDS, Smart Plan.

Principal Piping Design/piping Supervisor, Thechnip, Aromatics Plant, La cangrejera Veracruz, Mexico, PEMEX

START Date
END Date

I'm a Piping Designer, I have 34 years of experience in development of Chemical and Petrochemical projects. I live in Monterrey, Mexico. The last projects I have developed in Technip-Monterrey/Houston and KBR Monterrey/Houston (10 years)

And Ihave 11 years of experience with PDS, Smart Plan.