Artemis Systems Controller, Charlton Leslie Offshore, Amerada Hess/Rob Roy Conversion
START Date
END Date
This project was the largest semi-submersible floating platform conversion undertaken to date, consisting of circa 2 million direct manhours over an 18 month period.
The Artemis 6000 System contained a database of circa 60,000 items rolling up weekly to network and level 1 reports, and monthly by B of Q items for QS interim valuation reports. Also set up and utilised were computerised cable schedules, piping spools registers, hydrotest registers and a manhour recording system giving details of contract and additional hours expended on a weekly basis.