Planning Engineer, TUCN - Total Upstream Company of Nigeria, AKPO & USAN Operations
START Date
END Date
- Maintain ECP Integrated Schedule which contains:
- Carry-over/Completion works
- Site Modifications Requests
- Notification & request for assistance works
- Punch Lists
- Subsea activities – OIMR Vessels following Drilling sequence for installation of Xtrees, Jumpers & Flying leads
- AKPO Partial Shutdown schedule preparation & progress execution monitoring in Oct. 2010.
- AKPO Full-Field Shutdown Schedule preparation & progress execution monitoring in Oct./Nov./Dec.