Site Planning Engineer

Site Planning Engineer, MALAYSIA MARINE & HEAVY ENGINEERING SDN BHD, Gumusut Kakap Offshore Platform Development

START Date
END Date
Experience Hours (Planning & Scheduling)
2000

1. Prepared and updated workpack and jobcard for Fabrication of Gumusut Kakap Floating Production System

2. Monitored and maintained benchmarking for each fabrication discpline

Site Planning Engineer, SBM Offshore, Aseng FPSO Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1300

1. Integrated Project Master Progress Monitoring

2. Maintained and updated integrated activity planning

3. Supervised contractor reporting, progress and performance

4. Prepared weekly and monthly report to Higher Management 

Site Planning Engineer, Atkins Faithful & Gould, New King Abdulaziz International Airport Development Project

START Date
END Date

·        Preparation of a comprehensive cost and resource loaded contract baseline time schedule for the Aprons, Taxiways, Load Centers, Airside Storm water network (Pipe and box culverts), Blue Water Network, Airfield Ground Lighting network and the associated Vault Rooms, Glycol Network, 400Hz Network, Fuel Hydrant Network from the Fuel Farm, Fuel supply network from Aramco depot, GSE Tunnel/Ramps and security checkpoints, by reading the design drawings (70%).

SITE PLANNING ENGINEER, GCN, A28 - Viana/Caminha

R
Rui Gaiao 👤 Member for 22 years 10 months
START Date
END Date
Experience Hours (Planning & Scheduling)
250
Experience Hours (Cost Management)
750

INDUSTRY: Civil Engineering - Construction and Public Works
PROFILE: CASAIS SA, Eusebios SA, Gabriel Couto SA and Aurelio Martins Sobreiro Joint-Venture
ROLE: Construction Manager deputy with Planning, QSA and Quantity Surveying responsibilities

#PROJECT#

- EUROSCUT HIGHWAYS -A28 - Viana do Castelo/Caminha -. 58 Million EUR
Construction of 10Km of mountain highway, with 3 viaducts, 2 underpasses, access roads, drainage and electrical infrastructures and slope stabilization

. Leaded the QSA and Quantity Surveying departments, with 5 techniques
.

Site Planning Engineer, DSD Ferrometalco, 2x350 MW Thermal Power Project, 2x650 MW Thermal Power Project, Ammonia Nitrate Plant

A
AMR MOUSSA 👤 Member for 13 years 7 months
START Date

Ø  July  2012 till now     ( Planning  Engineer )

Project:EHC-LDAN Ammonia Nitrate Plant

Company:  DSD FERROMETALCO                  Client: HASSAN ALLAM Construction (HAC)

Site Planning Engineer, DSD Ferrometalco, 2x350 MW Thermal Power Project, 2x650 MW Thermal Power Project, Ammonia Nitrate Plant

A
AMR MOUSSA 👤 Member for 13 years 7 months
START Date

Ø  July  2012 till now     ( Planning  Engineer )

Project:EHC-LDAN Ammonia Nitrate Plant

Company:  DSD FERROMETALCO                  Client: HASSAN ALLAM Construction (HAC)

Site Planning Engineer, National Grid - Electricity East Alliance , National Grid - Refurbishment Norton Spennymoor 400kv and New Line Tees Crossing

START Date

·         Develop, optimise, and agree assigned project  programmes covering the construction aspect of the programme , including milestone definition/achievement, resource planning, cost control  and outage planning, to deliver the work with Asset Management, Network Operations, the Construction Programme Manager, Delivery Manager, Development Manager and Design Manager.

 

Site Planning Engineer, ITD CEMENTATION INDIA LTD., DAM,Canals, Bridges, Aqueducts and Road Project

START Date
END Date
  1. Activity wise planning and scheduling for the project using Primavera.
  2. Activity wise monitoring and preparation of Impact schedule programme using Primavera.
  3. Attending meetings with Client and co-ordinate the information to other departments.
  4. Progress monitoring and reporting to H.O with MIS formats.
  5. Finding out actual cycle time for major activities in the project.
  6. Taking photographs of all activities at site for Monthly progress Report for Client.