Senior planner engineer

Senior Planner Engineer, Worley, BHP Olympic Dam Project

X
xiao lian 👤 Member for 6 years 2 months
START Date
END Date
Experience Hours (Planning & Scheduling)
350
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

Senior Planner Engineer, Worley, Chengdu

Elkem Xinghuo Project Responsible for schedule setup and progress measurement setup for  Elkem Xinghuo Project.

Control Manager,Worley, Chengdu

BASF MDI-3 PLANT PROJECT Take the lead of control team to control the whole progress for BASF MDI-3 PROJECT. Be in charge of progress and cost control in PMC Chart.

Senior Planner Engineer, Worley, Chengdu

Senior planner engineer, Barrick Gold Corporation.-, Pascua Lama Project

START Date
END Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Forensic Analysis)
1000

March, 2006 – September, 2009 Barrick Gold Corporation Santiago

Pascua Lama Project

Planning and Cost Control Engi

Project Value: U$2.900.000.000.-

The main objective was to establish the Project Plan and budged, in order to determine the seasonality of the   project implementation; considering the physical progress and preparing a forecast for the completion date.