Senior Engineer Planning, ENGSOL, 220/132/33/22/11kV Substations
- Lead planning, scheduling and cost control efforts for all project phases. Maintain and analyze actual and forecasted schedules, cost and risk.
SITE PLANNING & EXECUTION OF RAW MILL BUILDING, TG BUILDING (TURBINE GENERATOR) BUILDING
INDEPENDENT RESPONSIBILITY FOR PLANNING, SCHEDULEING & EXECUTION OF WORKS ON SITE.
MICRO-PLANNING UP TO WORK BREAKDOWN LEVEL-7
MANNING ALLOCATION & PRODUCTIVITY ANALYSIS.
TIME STUDY ANALYSIS (THEORITICAL V/S PRACTICAL ON SITE)
DAILY MEETINGS W.R.T PROGRESS ACHIEVED V/S PLANNED WITH CLIENT & PROJECT MANAGER.
Leading role of Project controls engineer including Maintain Project schedule, review, analysis, EVM, suggest critial areas to project for timely corrective action. This role also includes project coordination with various internal departments.
During this role, i also learn various planning tools and attnded Primavera training P3 and then P6. Various other training on cost controls and Risk managment has been attended.
Prepares project control plans and detailed staffing utilization plans for discipline or specialty activities.
Assists in preparing schedule data for proposals or contract negotiations. Participates in developing and presenting training classes on designated subjects and on-the-job training for specific processes and practices.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.
Jun’11 – To Date LANCO Infratech Ltd Planning (Senior Engineer)
Project: Anuppur Thermal Power Project 2 x 600 MW (Phase-I)
Client: Moserbaer Projects.