Project Schedule Engineer

Project Schedule Engineer, CSL Behring Lengnau AG, CSL Behring Recombinant Facility

START Date
END Date

Project schedule engineer, member of a 7 head team for a large greenfield pharma project.

Project schedule development, maintenance, progressing for one building, from CC to CQV, handover. As well, CQV scheduler support.

Project Schedule Engineer, F. Hoffmann-La Roche AG, ADC 91

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Forensic Analysis)
500

Schedule setup - process, civil, automatization, qualification  - for a pharmaceutical brownfield project at Roche's Basel site. A pharma production building with ~15.000 sq.m., full GMP/GEP.

Project Schedule Engineer, Quality Planning Solutions/Turner Construction Company, Miami Intermodal Center, Miami International Airport

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
100

Schedule engineer for $300M MIC MIA, $50M MIC Station projects; P3 3.0, Digger

§  13,000 activity as-built schedule updated in weekly database copy,  2 sub-projects

§  Narrative and CPM analysis weekly and monthly submittals

§  Weekly owner schedule review meetings

§  ‘Last Planner’ (Lean Construction certified) & ‘Pull meetings’ with subs