PROJECT ENGINEER

PROJECT ENGINEER, Cekap Technical Services Sdn Bhd, 1. Detail Study of Failure Mode, Effect and Crtiticality Analysis for PM323 and PM 329 for SapuraKencana 2. Provision of Bathymetric Survey for Dredge Navigation Channel and Basin

A
Arif Sazali 👤 Member for 9 years 8 months
START Date
END Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

 CEKAP TECHNICAL SERVICES SDN BHD (August 2012 – Ongoing) Position: Project Engineer My roles & responsibilities involve planning, and monitoring on project execution, resource, and contract management as per following: · Strategic planning which includes setting up project goals, identifying project deliverables, setting up project milestones and develop projects tasks.

Project Engineer, Samsung Engineering & Construction, Saudi kayan Jubail, Riyadh Clean Transport Fuel CO2 projects

START Date
END Date
Experience Hours (Planning & Scheduling)
3000

1.   Worked as Project Engineer (Project Management Dept.) with Samsung Engineering Saudi Arabia in Kingdom of Saudi Arabia.

×    Responsible to review the design engineering activities and specifications of all mechanical, Steel Structural design, according to the requirements of the project, carried out by Vendors/ Subcontractors in all areas according to national and international Codes and Standards.

Project Engineer, Samsung Engineering & Construction, Saudi kayan Jubail, Riyadh Clean Transport Fuel CO2 projects

START Date
END Date
Experience Hours (Planning & Scheduling)
3000

1.   Worked as Project Engineer (Project Management Dept.) with Samsung Engineering Saudi Arabia in Kingdom of Saudi Arabia.

×    Responsible to review the design engineering activities and specifications of all mechanical, Steel Structural design, according to the requirements of the project, carried out by Vendors/ Subcontractors in all areas according to national and international Codes and Standards.

PROJECT ENGINEER, SNC Lavalin, sulfuric acid plant

START Date
Experience Hours (Planning & Scheduling)
850
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
250

Work with SNC Lavlin as Project Engineer< in the north of Sauid Arbia 

3 line 15,150-metric-tone-per-day sulphuric acid plant and two 75-MW power plants.

-Identifying the business needs, Developing Requirements, and define project phase and the sequence of the activities.

-Develop a detailed project plan to monitor and track progress -

Monitoring and managing change, risk, performance that could impact project scope.

Project Engineer, Hawaiian Dredging and Construction, Hyatt Regency Kauai

L
Lee Jones 👤 Member for 9 years 10 months
START Date
END Date
Experience Hours (Planning & Scheduling)
1200
Experience Hours (Cost Management)
600

Project Engineer for Hawaiian Dredging and Construction for construction of new Hyatt Regency Resort Hotel on Kauai, Hawaii.  Ordered materials, tracked costs and schedule for self-performed drywall work on 600 guest rooms and suites.  Coordinated subcontractors for finish trades on guest rooms and suites. 

Project Engineer, Philippine Ports Authority, Various Ports and Harbour Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

• Executed various construction projects on schedule with costs of $1M-$5M.• Well-versed in Bid-Build, Design-Build, EPC, and Public-Private Partnerships (P3) contracts.• Created project scope, activity lists, network diagrams and divided projects into phases.• Prepared procurement documents and evaluated contract docume