PROJECT CONTROL SUPERVISOR

Project Control Supervisor, ICA FLuor Daniel, •Grupo ICA, Residual water Re-Pumping system “La Caldera”, Ixtapaluca, Edo de Mex

START Date
END Date
Experience Hours (Planning & Scheduling)
700

Planning and Schedule Adviser, Delays and Claims Analysis, Risk Analysis

Project Control Supervisor, ICA Fluor Daniel, Grupo ICA, Mexico City Subway Line 12, México.

START Date
END Date
Experience Hours (Planning & Scheduling)
900

Planning and Schedule Consultans for Consortium Overall Schedule integrations, Delays, Claims and Risk analysis.

Project Control Supervisor, ICA Fluor Daniel, Indelpro. Propylene Production line II y Splitter Revamp; Altamira Tamaulipas, Mex

START Date
END Date
Experience Hours (Planning & Scheduling)
4150

Project Control. Planning and Schedule Lead, Plant Shut Down Planning coordinator, Progress Reporting

PROJECT CONTROL SUPERVISOR, Earth Gift Cooperation limited , SAUDI ARAMCO THIRD PARTY COGENERATION PROJECT

START Date
END Date
Experience Hours (Planning & Scheduling)
1250
Experience Hours (Cost Management)
1250
Experience Hours (Forensic Analysis)
500

• Prepare and review base line schedule. • Maintain and update actual & forecast schedule. • Prepare three look ahead schedules. • Update and monitor progress and cost of the project • Prepare and follow project monthly invoices. • Plan and distribute the work among construction mangers • Monitor and analyses daily progress and daily activates in site • Analyze progress delays and create recovery plans