Primavera Consultant

primavera consultant, Siemens AG, Tengizchevroil LLP – Sulphur Expansion Project

J
jean perrin 👤 Member for 12 years 11 months
START Date
END Date
Experience Hours (Planning & Scheduling)
500
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
600

Siemens project TCO Tengiz Chevron Kazakhstan 300 million

Consultant in Change management 

Primavera Consultant, AMEC, All Oil & Gas, Clean Energy, Greenfield and Brownfield Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
1000

Support and Product Development of Primavera EPPM applications. Integration with Legacy Systems. Product assessment (Third Party Software) fot the EMEA and Growth Regions

Primavera Consultant, AB ALSTOM POWER ltd, Several

START Date
END Date

Deployed in the Alstom Power HQ in Baden Switzerland as a Primavera Consultant, assignment was to deploy Primavera Portfolio Management applications worldwide in both Design and production facilities with the objective of producing a single schedule for Power Station EPC contracts. This involved liaison with the Design and Production facilities on a worldwide basis and involved assessing current schedules and deploying process improvements to the planning community.

Primavera Consultant, British Energy / Morson International, All Engineering Outage and Development projects

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
1400
Experience Hours (Forensic Analysis)
100

Energy I was commissioned to re-organise the planning processes and merge two divisions into one so that they used standard process. There are over 80 planning staff located at 8 nuclear power stations, one coal fired station and three supporting business units throughout the UK.

The first task was to examine the existing processes and procedures, in addition a health check was carried out on the Primavera infrastructure, including a thorough assessment of data integrity and schedule integrity.

Primavera Consultant, Alstom Power International, Global Deployment of Primavera

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
300

The assignment for Alstom Power involved deployment of Primavera throughout the Engineering and Manufacturing facilities worldwide. Working at their HQ in Baden Switzerland the initial task involved producing a specification for database configuration to be utilized as a global standard. This was achieved by facilitating workshops with the stakeholders in USA, Germany, Indonesia, India, China, Portugal and Czech Republic.

The next stage was to standardize processes throughout including resource management, schedule integration and machine shop capacity planning.