Planning & Project Controls

Planning & Project Controls, Arabian American Oil Co. (ARAMCO)-Saudi Arabia, Master Gas System 56

START Date
Experience Hours (Planning & Scheduling)
10150
Experience Hours (Cost Management)
10050
Experience Hours (Forensic Analysis)
5450

o      Manage the overall project in respect of all project management phases such as planning, execution, monitoring, controlling, changes controls and closeout.

o      Providing planning and scheduling support as required during Front End Engineering Design (FEED), Detailed Design and Execution of major capital projects in the Company's Capital Program.

Planning & Project Controls, Chicago Bridge & Iron (CB&I), Various projetcs

START Date
END Date
Experience Hours (Planning & Scheduling)
6000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
1800

Planning & Project Controls Engineer - Planning/scheduling, Earned value management/ progress reporting, Labour forecast. Cost management.

Planning & Project Controls, EDF, Nam Theun II Project

A
Ayman Assal 👤 Member for 18 years 6 months
START Date
END Date
Experience Hours (Planning & Scheduling)
2800
Experience Hours (Cost Management)
1700
Experience Hours (Forensic Analysis)
1100

Duties

·  Coordinate management of the related project directed toward strategic business and organizational objectives.

·  Plan and provide work direction as required for the preparation of planning and scheduling control systems to evaluate and improve the efficiency of their project execution.

·  Provide staff guidance to Engineering and Construction supervisors by analyzing and evaluating all pertinent data.

Planning, Planning & Project Controls, Assistant Manager, GMR GROUP, GMR Hyderabad International Airport, GMR Delhi International Airport

START Date

I have 5 years of professional experience in the areas of Project Execution, Project Co-ordination, Planning etc.

Areas of work
a. Power plant
b. Airport
c. Office buildings