Planning Manager

Planning Manager

Planning Manager, AMEC, Sub Surface Lines Power Upgrade

START Date
END Date

Planning & Reporting Manager on Power Upgrade Project for Amec

 

  • Negotiated with client to create new SSL Scoping & Development programme to facilitate requirements of MPD, EV and period reporting.
  • Managed production of Design & Build programmes for client to use in ITT successfully recovering lost time in the delivery milestone.
  • Improved relationship between client & contractor.
  • Managed a team of ten planner

Planning Manager, JSC OGCC KazStroyService, Gas Treatment Plant Project, Bitumen Plant Project, Gold Refinery Project

START Date
END Date

Planning Manager and Project Coordinator for Gas Treatment Plant Project, Bitumen Plant Project and Gold Refinery Projects in Kazakhstan.

Planning Manager, SITA, Dublin Airport Terminal 2

START Date
END Date

SITA employed me to manage the plannning associated with the £36M Specialist Systems works at Dublin Airport, Terminal 2. This involved planning of the design, procurement, installation, systems integration, and commissioning & handover phases. Particular attention was paid to the Airport critical systems of CCTV, Access Control, Security Search, and the new US Customs and Border Protection (SITA bespoke system) Baggage Image & Location System.

Planning Manager, Thales, FFG Upgrade

START Date
END Date
Experience Hours (Planning & Scheduling)
8200
Experience Hours (Cost Management)
3150

Led a team of six planners and three schedulers to ensure all activities relating to FFG installation were planned, scheduled, monitored and controlled in a cost and schedule effective manner.  Ensure measurement of progress through appropriate systems and processes and actively address situations of significant deviations from plan in coordination with Project Manager. Maintain cost and schedule visibility to all levels of management.

Specific Responsibilities

Planning Manager, Al Habtoor Engineering Enterprises, City Centre Expansion Project

START Date
END Date

Construction of 5 Towers of 54 Storeys each in Doha, Qatar
JOB DESCRIPTION:
•Prepare Clause 14 Programme of Works in Primavera P3 or P6 formats.
•Supervises planning engineers in weekly updates of the construction progress and prepares construction updated schedules using Primavera Project Planner.
•Monitor actual accomplishment in reference to the contractual Clause 14 P3 Program and or Balance-to-Complete P6 Programme.
•Liaise with Project Manager and formulate strategies in order to meet his target program.
•Manages sub-contractors schedules, resources and updates.

Planning Manager, ALSTOM Transport, Incheon Airport Railway Project

START Date
END Date

Incheon Airport Railroad Project, Korea



Developed Programme/Schedule:

Baseline Contract Schedule (Primavera P3)

Progress Monitoring Tools for Manufacturing & Delivery (Excel)

Progress Monitoring Tools for Installation (Excel)

Track Related Installation Programme (Excel)

Test and Commissioning Schedule (Primavera P3 & Excel)



Reporting:

Monthly Progress Report

Monthly Progress Presentation

Weekly Progress Report

Critical Path Analysis

Planning Manager, Senior Planner, Larsen & Toubro Construction Co. KEO Internationl Consultant, ABB Lumus Global Corp., High Rise Building, Metro Rail, Petrochemechal & Refinery, Aiports and Infra

C
Claro Diez 👤 Member for 19 years 11 months
START Date

SUMMARY OF EXPERIENCE:

Thirty One years of continuous experience in Project Management, Construction Management and General Contractors as Planning Manager, Senior Planner /Senior Cost Estimator and Senior Quantity Surveyor. The projects that I was involved with are Metro Rail, High-Rise Buildings, Refinery, Petrochemical and Terminal Airport, Hospitals, Pipelines & Pumping stations, Utility Tunnels/Micro Tunneling and Infrastructure projects.

Planning Manager, Group Five Projects Pty Ltd, Saldanha Steel Project

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
400

Started with development of coding structure for consortium and level 3 programs for “Saldanha Mechanical Contractors”, written in Primavera ver 2.b. This contractual program had to be integrated with other contractors on site due to the fast track nature of the project and had to be totally network compatible so that all contractors on site could update one integrated schedule. This schedule became contractual level 3 programs for the consortium.