PLANNING ENGINEER

Planning Engineer, VELUX, Project office

START Date
END Date

Planner at the VELUX project office in the development department. I was employed as planner in a project office supporting approximately 80 project managers. The project office was a part of VELUX Product Development. The product development follows the Stage-Gate model, and the planning was carried out in Primavera. My main task was support to Project Managers regarding
Primavera and Planning in general. Furthermore, I provided the Gatekeepers and Management with data enabling them to prioritise the projects and giving them “GO” or “Kill” options.

Planning Engineer, Galfar Engineering & Contracting SAOG, Up-gradation of existing service connections

START Date

• Level 4 Project baseline schedule

• Mobilization plans.

• Analyze the Critical Path using CPM / PERT.

• Progress tracking and manpower productivity by daily / weekly tracking sheets.

• Manpower histograms and progress curves for analysis.

• Look ahead programs, including clash checks to ensure readiness to progress.

• Site material planning and Quality management system.

• Prepare risk mitigation plans and assess regularly.

• Assess the progress of project using Earned Value Management System.

PLANNING ENGINEER, Doha Petroleum, EPIC & Construction projects

START Date
END Date

1) Participate in bid and tender meetings, site visit and queries
2) Review of contracts, scope of work
3) Prepare execution plan, WBS and schedule of activity based on contract scope
4) Coordinate with estimating and operational group for budget and work schedule activity
5) Prepare cash flow based on estimated budget and integrate to schedule for resource loading
6) Monitor, track and update project status, and preparation of report for submittals
7) Perform schedule analysis for delays and impact to the existing schedule
8) Preparation of mitigation, recovery plan, a

Planning Engineer, N/KOM, Dock Gate Projects, LOR Barge & etc.

START Date

*Experienced in Civil, Road, Building Construction, Ship Building and Marine Works.
*Experienced in Electro-Mechanical for Construction.
*Experienced in Cost and Estimates.
*Experienced in Project Construction Management (using P3/P6) and MS Project.
*Experienced in Safety and Security, Risk Management, Safety and Health regulations and laws pertaining to the workplace environment.
*Experienced in Computer Aide Design (Auto-CAD 2007, WS, Excel).
*Creative, preservative, can work well under pressure.

PLANNING ENGINEER, Gammon & Billimoria LLC, 31nos. G+4 Residential buildings

START Date
END Date

Project: International city Package 07

Client – Nakhel, Dubai

31 residential Apartments for International city developed by Nakheel at Dubai, U.A.E.

Project Value : AED 400 Millions

Achievements: Prepared micro planning for all the activities and closely monitored the same, flagged up the issues and risks involved so that achieved the first 2 miles stones of the project.

Introduced new and user friendly practice for easy and close monitoring of activities.





Responsibilities:

Planning Engineer, Al Ahmadiah Contracting & Trading, Aircraft Hangar, Infrastructure Development Works

F
Farhan Khan 👤 Member for 17 years 4 months
START Date
END Date

Project Undertaken: Infrastructure Development works for the Jaber Al Ahmad City project N1 & N3. The proposed area of the project is 982 hectares that will accommodate approximately 5700 dwelling units of Kuwaiti foundation.

Work included Planning, Scheduling and Controlling of the whole project to meet the objectives managed by senior management. Prepare various schedules and reports for Management and clients on the revision to all scope, estimate and schedules. Quantity Calculations, Technical tender evaluations. etc.

PLANNING ENGINEER, Delta Afrik Engineering, Onshore and Offshore

START Date

EXPERIENCE
     (DeltaAfrik Engineering Ltd, LAGOS) Planning Engineer 2008 - 2010

PROJECTS – Onshore / Offshore Security Upgrade Project and Critical Crude Pipeline Replacement Project.

PLANNING / SCHEDULING
Performs project planning tasks and schedule development and update.

     Prepares and manages overall master project schedule integrating the project Work Breakdown Structure using an appropriate scheduling software package (Primavera)
     Planning & Scheduling of Conceptual

Planning Engineer, IMCO Engineering & Construction Company, Oil & Gas Pipeline, Storage Tank, Bulding, Electrical & Instrumentation, Flare, Injection Quills

START Date
  • Preparation of the Project Master Schedule, Summary curves.
  • Preparation of detailed Project Execution Plan, S-Curve, Resources and Manpower Histogram in Consideration with the Site logistic Plan.
  • Preparation of Recovery schedule as required.
  • Preparation of Tender & Shutdown Schedule.
  • Preparation of Asset capitalization, Data Acquisition (CMMS) for SAP, Close out Report, Invoices & Project Dossier.
  • Preparation, Review & Publishing of MIS & Monthly, Weekly, daily reports and Presentations, using bar Charts, S-­Curve and presenting t

Planning Engineer, Saipem S.p.A., Soku Gas Plant (Shell Nigeria)

START Date
END Date

I was assigned as Planning Engineer in the Project Control Department at the Saipem Corporate Headquarters in San Donato, Milan. I was tasked to help in the development of Planning Procedures and Construction Schedule of the Soku Gas Plant for Shell Nigeria and the Offshore Pipeline, Berths Installation in Jamnagar, India for Bechtel/Reliance Petroleum Ltd.

I also prepared Construction Schedule for Bid Proposal of Texaco Exploration Myanmar Inc. 30” Pipeline & Valve Station Installation and the Water Pipeline System of Venezuela.