PLANNING ENGINEER

Planning Engineer, BUTEC SAL, Electricity Capacity Expansion Ph.VIII

A
A. L. 👤 Member for 16 years 1 month
START Date
END Date
Experience Hours (Planning & Scheduling)
1400
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
2800

v  Visited the project site regularly for periodic progress report and evaluation.

v  Worked with Project Manager for support in the productive and timely completion of the project.

v  Provided BOQ of major projects to Bids Team for preparation of tenders. Projects tendered include NDIA C-II Airline Support Facilities (Doha), Developpement du Champ de Rhourde Nouss (Algeria).

Planning Engineer, BUTEC SAL, Electricity Capacity Expansion Ph.VIII

A
A. L. 👤 Member for 16 years 1 month
START Date
END Date
Experience Hours (Planning & Scheduling)
1400
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
2800

v  Visited the project site regularly for periodic progress report and evaluation.

v  Worked with Project Manager for support in the productive and timely completion of the project.

v  Provided BOQ of major projects to Bids Team for preparation of tenders. Projects tendered include NDIA C-II Airline Support Facilities (Doha), Developpement du Champ de Rhourde Nouss (Algeria).

Planning Engineer, Saudi Oger Ltd., KAEC - King Abdullah Economic City.

START Date
END Date
  • Monitoring of the programme and re-planning - if needed – during the project life cycle.
  • Prepare, review and issue daily, weekly and monthly reports as per the contract and the required internal reports to Project Manager (PM) and/or management to highlight areas of concern, programme slippage and project performance indices (KPI).
  • Prepare two weeks look ahead schedule and distribute to construction team and follow up / support to achieve it.

Planning Engineer, Daewoo E&C, EGTL (Escravos Gas to Liquid Project)

START Date
END Date
  • Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, Architecture, UG/AG Piping, Mechanical, Electrical, Instrument, Insulation, Painting & Pre-Commissioning).
  • Developing of EPC Master Schedule using Primavera P6 Software , up to Level 5 as per contract requirement
  • Involved in preparation of Progress Measurement of Engineering, Procurement and Construction work, along with invoice submission.
  • Weekly/Monthly/Daily reports generation including ‘S’-curves for client & management review.
  • Resource planning c

PLANNING ENGINEER, SK Engineering & Construction, Takreer Refinery Expansion Project

START Date
END Date

Ø  Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, Architecture, UG/AG Piping, Mechanical, Electrical, Instrument, Insulation, Painting & Pre-Commissioning).

Ø  Able to understand the Technical Scope of work, Scheduling / Planning the appropriate set of activities and ensuring on timely completion of Project by Operating  Primavera Software.

Planning Engineer, Integral Services Co. W.L.L. (ISCO), Kuwait National Petroleum Company (K.S.C.) Clean Fuels Project (CFP)

START Date
END Date

Ø  Main scope includes Procurement and Construction work (Temporary facilities, Shutdown Tie-in work, Civil, Architecture, AG Piping, Mechanical, Electrical, Instrument, Insulation, Painting & Pre-Commissioning).

Ø  Able to understand the Technical Scope of work, Scheduling / Planning the appropriate set of activities and ensuring on timely completion of Project by Operating  Primavera Software.

Planning Engineer, Penguin Engineering & Construction Pte Ltd, Multiple Projects - Green & Brownfield Developments

N
Nithin Raju 👤 Member for 12 years 2 months
START Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
5000
  • Plans, schedules and arranges the technical & management aspect of projects.
  • Project cost estimation including manpower, material & equipment.
  • Involves in planning/progress meeting with the clients and liaise with them for smooth execution of projects.
  • Develops schedules/estimates for projects and tendering.
  • Frames work break down structure (WBS) for projects based on the scope.
  • Monitors baseline schedule and records project progress.
  • Prepares project progress report for clients as well as the internal management.
  • Assists

Planning Engineer, PT. Adhi Karya Construction Division, EPCC Melati Margonda’s Apartments

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Forensic Analysis)
1500

• Planning, scheduling and updating Master Schedule (Level 1 – 2) and detail schedule (Level 3 - 4) and also S-Curve.

• Review, monitoring and preparing project schedule report summary by weekly and monthly (including Progress Claim & Invoice Monthly Report) of Master Schedule which have been assigned.

• Coordinate with Procurement and Logistic team to monitor material preparation before construction works.

• Coordinate with Construction team and sub Contractor to achieve the target schedule as per contract milestone

 

PLANNING ENGINEER, IMCO Engineering and Construction Co. WLL., Maintenance and Construction Project

START Date
Experience Hours (Planning & Scheduling)
19650

A well presented and experienced PlanninG Engineer with over more than 9.8 years of extensive experience in the filed of Maintenance of Refinery Equipments and Execution and Shutdown Planning, Construction Project Oil and Gas Field, Oil and Gas Facilities Maintenance.

  • Planning and Scheduling
  • Maintenance of Refinery Equipments
  • Routine, Preventive ,Corrective and Shutdown Maintenance
  • Trunaround and Unscheduled Shutdown
  • Contstruction Project in Oil and Gas Field
  • Project Execuation
  • Material Management