Planner, Westinghouse Brakes & Platform Screen Doors, Managing engineering department projects and resources

START Date
END Date

Managed the projects and resources within the engineering department.

Including production of new programmes, updating and monitoring existing programmes and earned value reporting.

All projects were resource and cost loaded and the programme resources were managed in the department by leveling resources using Primavera software. Employees booked completed timesheets using Primavera and this time was allocated to specific activities in each programme.

Planner, Under BAPCO planning team, M/s Ramsis Engineering and Co W.L.L, Bahrain, TA-2007

START Date
END Date

 

Planner for Exchanger & Furnace Maintenance works in TA-2007 under BAPCO planning team

 

  • Preparation of T/A hourly schedule base line schedule
  • Resource Loading and resource levelling
  • Preparation of 'S' Curve based on Man-hours
  • Monitoring the progress in Hourly basis.
  • Preparation of Daily progress report & area of concern
  • Analyze the c

Planner, Consulting, KBR, Lower Lea Valley Underground Power Lines

START Date
END Date

Lower Lea Valley Underground Power Lines – Tunnels, 2004 - 2005

Project planning for this cable tunnel project which was being developed in support of the London Olympics. Planning included producing five different options for the construction phases of this LDA sponsored work in Primavera 3e/c (P5). This project consists of two 6km tunnels under east London, currently under construction.

Planner, Scottish Power, Strategic Transactions

START Date
END Date

Working for Innovation Business Vision which is a project management/project control consultancy. The following project was undertaken on their behalf.

Working as a planning consultant at Scottish Power. Tasks included creating, maintaining and updating project schedules and associated progress measurement/reporting structures for several wind farms.

Planner, Shell, Various Maintenance Projects

START Date
END Date
  • Amec Process & Energy, City Gates, Nigg, Aberdeen (Theddlethorpe based) Aug 95 – Oct 99
  • Shell Operating Co. P.D.O. PO Box 81, Muscat 113, Sultanate of Oman June 1993 - July 1995
  • Shell (UK) Expro, PO Box 4, Lake Lothing Depot, Lowestoft, Suffolk. April 1990 - May 1993
  • S.L.P. Engineering Ltd, Hamilton Rd, Lowestoft, Suffolk. April 1989 - March 1990
  • S.L.P. Engineering Ltd, Hamilton Rd, Lowestoft, Suffolk. August 1980 - October 1982