Lead Scheduler/Planner

Lead Scheduler/Planner, Turner & Townsend Inc., San Francisco International Airport T1 Redevelopment Program

START Date
END Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Forensic Analysis)
500

Development and implementation of the overall program schedule for the T1C Redevelopment Project.

Identification of the critical and key interface touch points.

Prepare the weekly and monthly progress reporting and implementation of key KPI dashboard that tracks the major bulk quantities to aid in progress reporting to senior management.

Develop & Support the SFO Airport ORAT team commisisoining & go-live execution schedule.

Lead Scheduler/Planner, Burns & McDonnell, Substation & T-Line

START Date
END Date
Experience Hours (Planning & Scheduling)
20000
Experience Hours (Cost Management)
10000

► Developed EPC level II and III schedules in coordination with program management and EPC while following client’s project delivery model - PDM.

► Supported project controls project execution plan – PEP.

► Supported client project controls policies and procedures – P&Ps revisions.

► Conducted bi-weekly schedule update meetings.

► Performed earned value analysis (SPI) based on rules of credit – ROC and established thresholds.

Lead Scheduler/Planner, Parsons International Limited, CP 133 Project - Hamad International Airport (HIA)

START Date
Experience Hours (Planning & Scheduling)
9000
Experience Hours (Cost Management)
9000
Experience Hours (Forensic Analysis)
7000

Role and duties relating to claims and delays
• Review and monitor early warning notifications for cost and delay.
• Compare approved baseline programme with look-a-head and other short term programmes to monitor progress and potential delays.
• Maintain log of delays and update monthly.
• Review submitted notices of Delay and respond to Contractor.
• Carry out merit assessment of submitted delay claims (interim and final particulars) and check for compliance with the Contract in conjunction with Contracts Manager.

Lead Scheduler/Planner, Parsons, Abu Dhabi International Airport Expansion (US$6.8B) – Runway, Taxiway, Apron and Terminal Buildings

START Date
END Date

Provide planning leadership and support in the development and coordination of the master construction program.  Prepared and maintained the Master WBS and EPS structure, fortnightly progress reports and overall program code structure. Reviewed contractor’s delay claims and provide written claims analysis and recommendations to the project managers.

Lead Scheduler/Planner, Samsung C&T, New Ulaan-Baatar International Airport (NUBIA) Project

R
Roy K 👤 Member for 12 years 7 months
START Date

·         Lead Scheduler for NUBIA(New Ulaanbaatar International Airport) Construction Project in Mongolia worth 0.6 billion USD

·         In charge of designing master schedule from the initial stage using Primavera P6

Lead Scheduler/Planner, Samsung C&T, New Ulaan-Baatar International Airport (NUBIA) Project

R
Roy K 👤 Member for 12 years 7 months
START Date

·         Lead Scheduler for NUBIA(New Ulaanbaatar International Airport) Construction Project in Mongolia worth 0.6 billion USD

·         In charge of designing master schedule from the initial stage using Primavera P6