Lead Planning Engineer, Foster Wheeler, NANAHAI PROJECT CHINA (CNOOC-SHELL)
JUNE 2003 TO DEC 2004 Foster Wheeler<?xml:namespace prefix = o />
&nb
JUNE 2003 TO DEC 2004 Foster Wheeler<?xml:namespace prefix = o />
&nb
Responsible for the preparation of Level 3 Critical Path Networks and Bar Charts integrating separate multi-disciplinary railway design and construction programme, ensuring co-ordination especially of signalling design and construction for the Sandbach to Wilmslow Resignalling Scheme.
Gwynt-y-Mor Offshore Wind Farm
Responsible for preparation of Level 2 & 3 cost loaded programmes, “S” Curves and Earned Value measurement for a £120m wind farm off the coast of North Wales.
Greater Gabbard Offshore Wind Farm
Full Planning and Controls responsibility for Client on the Fabrication/Commissioning Phase
Full Planning and Controls responsibility for Client on the Detail Design Phase
Site Engineer- 2004-2008
Design Engineer- 2008-2009
Plannner/Scheduler- 2010-2011
Lead Planning/Scheduling Engineer- 2011 to Present.