Lead Planning Engineer

Lead Planning Engineer, Black & Veatch, Europe Larger Combine Heat and Power Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
5000
Experience Hours (Forensic Analysis)
5500

Conoco Phllips Oil & Gas Immingham ICHP2  EPC Project of 412 Mega Watt 

u  Managing EPC Program of 8,529 activities of construction, engineering and procurement in Primavera. Project contains 17 sub-projects and 9 sub-contractor.

u  Integration of sub-contractor projects into main project.

LEAD PLANNING ENGINEER , ABENGOA (BEFESA AGUA), Madrid (Spain), EPC project of desalinization plant of Ténès (Algeria), EPC project of desalinization plant of Honaine (Algeria)

L
LUIS PEREZ 👤 Member for 14 years 3 months
START Date
END Date

EPC project of desalinization plant of Ténès (Algeria) with a budget of 240 Million USD with a design specification for desalinization water rate of 200.000 m3 of potable water per day for 2 million people in the Nord of Algeria.

EPC project of desalinization plant of Honaine (Algeria) for the JV company between Abengoa and Sacyr with a budget of 180 Million USD with a design specification for desalinization water rate of 180.000 m3 of potable water per day for 1.5 million people in the Nord of Algeria.  

Lead Planning Engineer, Cimac Electrical and Automation W.L.L.,, automotive industry

S
sugu maran 👤 Member for 14 years 6 months
START Date

·         Preparation of Project Schedule as per the Scope, Schdule maintain and update, and variance explanations.

·         Preparation of Detailed plans & Level-4 Schedule (As per Work breakdown Structure)

·         Preparation of Daily, 3 week Look ahead, Monthly Plan & progress Reports.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.