Forensic Planner

Forensic Planner

Forensic Planner, FAST Consortium, Riyadh Metro

START Date
Experience Hours (Planning & Scheduling)
2800
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
3300

- Assess subcontractors' EOT Claims and prepare rebuttals

- Prepare Coutnerclaims

- Prepare EOT Claims

- Support project control and planning team 

- Support Contracts / Legal Counsel team

Forensic Planner, Resolute mining, Syama Redevelopment Project

START Date
END Date
Experience Hours (Forensic Analysis)
350

Syama Redevelopment Project Gold Project Upgrade in Mali, West Africa.

Forensic Planner, (Specific Assignment), 10/2009 to 12/2009

Engineering delivery Claim preparation with Clayton Utz on behalf of owner. Assignment to introduce “for construction” drawing deliverables into baseline and As-Built schedule.

Forensic Planner, Brookfield Multiplex, Maundering Weir Water Treatment Plant Project

START Date
END Date
Experience Hours (Forensic Analysis)
750

Maundering Weir Water Treatment Plant – 165,000 Cubic Meters of water per day Water Treatment Plant.

Forensic Planner, (Specific Assignment), 02/2012 to 06/2012

Integrate Bill of Quantity data to progress schedules to assist client in development of Extension of Time claim case due to large change in scope and delay in design

Forensic Planner, CTEC, Merredin Power Station Project

START Date
END Date
Experience Hours (Forensic Analysis)
200

Merredin Power Station Project. 82MW PowerStation Project in Western Australia.

Forensic Planner, (Specific Assignment – Part time consulting role)07/2012 to 09/2012

Defense EOT claim preparation for client against contractor due to late delivery of equipment

Forensic Planner, Ertech, Marandoo Dewatering Project

START Date
END Date
Experience Hours (Forensic Analysis)
1250

Marandoo Dewatering Project – 24km pipeline with 27 bore pumps, Transfer & booster pump stations in Western Australia.

Forensic Planner, (Specific Assignment) 06/2013 to 03/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Forensic Planner, Ertech, Chevron Wheatstone Project

START Date
END Date
Experience Hours (Forensic Analysis)
150

wheatstone villageChevron Wheatstone Construction Village Buildings & utilities Project. Western Australia.

Forensic Planner, (Specific Assignment), 01/2014 to 03/2014

Preparation of Extension of time claim schedule in “Impacted as Planned” format.

Forensic Planner, PIHA, RIO-TINTO Cape Lambert Expansion Project

START Date
END Date
Experience Hours (Forensic Analysis)
600

RIO-TINTO Cape Lambert Services Contract Construction Project of Piping and Cable infrastructure at Point Sampson in Western Australia.

Forensic Planner, (Specific Assignment), 08/2013 to 06/2014

Preparation of Extension of time claim and support in Mediation process and conclusion