Claims Analyst, CT Summation Case Management Database, Senior Construction Consultant, TDF, LLC, Washington Metro Area Transit Authority Orange Line Extension Claim
START Date
END Date
Experience Hours (Planning & Scheduling)
800
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
500
Construction Consultant, P5 As-built scheduler for defense $30M litigation of $200M WMATA project; CT Summation software
§ 25,000 activities scheduled from inspection dailies into as-built
§ Develop codes and filters, code activities 8 ways, global code changes for improved as-built analysis
§ Review business processes, spec and 300K image project record for claim analysis
§ First draft of report summarily ended claim, adjudication lower than owner’s initial offer