Development and maintenance of Project Control Schedule (PCS) in the Project Control (P6) database in accordance with appropriate procedures, guidelines and instructions. Updated and progressed programmes at a minimum of 4 weekly intervals in line with Crossrail’s timetable of reporting
Ensured that project schedules accurately reflect the scope of the project in accordance with an agreed WBS and are of sufficient detail to enable project progress to be accurately monitored, reported and communicated
I am a self-motivated professional who excels when working in a team environment. I am adept at working to tight deadlines using my skills, experience and knowledge to achieve the requirements of the role. I enjoy a challenge and have the ability to influence others to ring the overall benefit to a project or a client. I have a track record of planning on high profile, complex projects over my time in the rail sector, as well as vast transferable experience within other industries.
Produced tender programmes and progressed construction progress on smaller value projects initially.
Following the win of a design and build contract for Sloane Square and Westbourne Park modernisation our team was relocated to Glasshouse to work closely with LUL on the design and implementation of these projects.
Took design from Riba D to completing Riba F (construction design sign off) before Metronet went bust and the projects were shelved.
WOrking on behalf of the client (London Underground) our team was managing the main contractor undertaking the upgrade of the existing ticket office and the construction and fit out of a new ticket hall and ticket office to serve the Distruct and Circle Line platforms.
I reviewed the main contractor programmes, for my sections, in P3 and then converting these into P6 and updating the programme given to LUL.
I was responsible for the extension of the existing ticket hall and the fit out of the new D&C line ticket hall and ticket offices.
Working on behalf of the client (London Underground) our team was managing the main contractor undertaking the upgrade of the existing ticket office and the construction and fit out of a new ticket hall and ticket office to serve the Distruct and Circle Line platforms.
I reviewed the main contractor programmes, for my sections, in P3 and then converting these into P6 and updating the programme given to LUL.
I was responsible for the extension of the existing ticket hall and the fit out of the new D&C line ticket hall and ticket offices.
Project Planner on: Stalybridge Signalling Enhancements GRIP 4, £295k value, produced resourced and fully costed multi-disciplinary tender programme and maintained and progressed the Live version in liaison with engineers. Plumstead Sidings Critical Advanced Work, GRIP 4 & 5, removal of sidings and buffer stops, £180k value, produced resourced and fully costed multi-disciplinary tender programme and maintained and progressed the Live version in liaison with engineers. Salisbury Signalling Enhancement GRIP 4, £175k value, produced resourced and fully costed multi-discipl