Oil / Gas / Power

Lead Planning Engineer, Saipem S.p.A., Chirag Oil Project (COP)

START Date

 

During the initial phase after contract award: ensure the implementation of the Planning and Progress Control System; in particular:

- Set-up type/ levels of schedules and the Progress Measurement System considering Project complexity, areas of risks, policy duration, in compliance with the Project Breakdown Structure, the internal standards and the Contract specifications.

- Interface with other Company Functions or Discipline Leaders/Supervisors to built u

Core Team Senior Planning Engineer, Descon Engineering Limited, BHP Zamzama Field Expansion Project, Combined Cycle Power Plant

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
2000

Resolution of issues in the implementation of Project Management Systems

Coordination with site project planning team

Resolution of recourse requirement issues

Progress Reporting to stakeholders

Planning Engineer, SAUDI ELECTRICITY COMPANY (Manpower Support by Energy Resources Development Co. Ltd. – TAACA), Installation of Turbine Inlet Air Cooling at Faras & Shedgum Power Plant CN. 30721071/00, Installation of Turbine Inlet Air Cooling at Arar &

START Date
END Date

Job Description:

  • Review of PTS – Project Technical Specification, instruction to bidders, summary of scope of work, attachments schedules and other project schedules such as contract action plan, critical milestones dates, procurement schedules and other relevant project schedules.
  • Responsible in reviewing and responding to contractor clarifications and technical queries relating to project schedules.
  • Prepare a brief summary schedule for overall project schedules using Microsoft Projects.
  • Prepares a wee

Planning Engineer, SAUDI ELECTRICITY COMPANY (Manpower Support by Energy Resources Development Co. Ltd. – TAACA), Installation of Turbine Inlet Air Cooling at Ar’ar & Al-Jouf Power Plants CN.30721192/00

START Date

Job Description:

  • Preparing a monthly internal Project Management Team (PMT) project monthly report with incorporating design & engineering report’s consisting of: Project progress and schedule, progress summary & analysis, main activities completed & planned, areas of concern and action taken, project financial status, overall progress s-curve, summary & document status list, update the P6 schedule for overall & deliverables issued and invoice tracking registry.
  • Review and monitoring of contracto

Site based construction planner, Tracey Brunstrom & Hammond, Colongra Peak Power Gas Turbine

START Date
END Date

The majority of Andrew’s work has included:

 

  • Strategic Programme Planning and Programme Critical Path Analysis

 

Experience in the preparation of program analysis of scope and dependencies mapping, to identify critical path for complex programs of works

 

  • Programming, Time Control and EOT Analysis

 

Experience in the p

Project Planner/ Scheduler, Aker Solutions, Kashagan Development Project, Offshore

START Date

Company                               : Aker Solutions Contracting AS

Type                                : Heavy Construction – Oil & Gas (EPC Contractor).

Project    &nb