Claims Analysis Planner, AMEC, Longannet Power Station - FGD

E
Eden Day 👤 Member for 15 years 10 months
START Date
END Date

I spent four months assisting on a claim for the project. This included the production of a P3 programme which visualised the historical data collected in the analysis of many drawings, documents and the contract. Utilising my extensive knowledge of Earned Value allowed me to clearly analyse data and S-curve’s, ensuring I was fully prepared for discussions with the project manager and confident presenting to the client. I also often progressed the program actuals using P5 and updated the expended man hours on a weekly basis.

Forensic Claims Analysis Planner, AMEC, Kilroot FGD Claim

E
Eden Day 👤 Member for 15 years 10 months
START Date
END Date

As Forensic Claims Analysis Planner on the Kilroot FGD project, I was working with a team of ten core persons including legal advisors to produce a model with audit trails and other required evidentiary support to form a successful legal case.

Engineering Planner / Scheduler, AMEC Energy Services UK, Multiple Projects in Oil and Gas / Nuclear

E
Eden Day 👤 Member for 15 years 10 months
START Date

In my role as Engineering Planner I am responsible for the ongoing update and revision of existing schedules and the development of new schedules for all engineering disciplines, primarily on Oil & Gas / Nuclear projects. I also develop EPC schedules in accordance with bid and tender requirements. Another responsibility is the tracking of CTR Deliverables, plus forecasting remaining durations and costs accurately.

Project Controller, AMEC, Longannet Power Station - FGD

E
Eden Day 👤 Member for 15 years 10 months
START Date
END Date

Managing the production of a Level 5 commissioning programme to be integrated into the master delivery programmes, working as Project Controller at the Longannet Power Station, Scotland. Constant communication with the Commissioning Manager as well as daily meetings with the project team allow me to be kept up to date of current progress and able drive the planning teams within the joint venture to implement the solution both accurately and correctly. I also frequently interface with the client in a formal setting.

Project Controller, AMEC, DOW De-Commissioning Project

E
Eden Day 👤 Member for 15 years 10 months
START Date
END Date

Working as Project Controller based at the DOW Chemicals EOEG Plant on the Wilton site, I managed the production of a fully resource loaded Level 5 Decommissioning programme with a value of £7million for Process Division. As part of this I am the first AMEC employee to successfully use the PICS database system and Primavera 6 together. This involved using the SDK to automate the integration between MS Access & P6.

Planning Manager, Oil Turbo Compressor Construction, Electro Compressor Station of West Ethylene Pipeline Project, Three Gas Compressor Station on IGAT 8 Pipeline

START Date

Highlights & Achievement:

 

  • Run the primavera contract management to restore and retrieve the documents in EPC project
  • Practicality analysis the risk of the gas station schedule and report to senior management
  • Train the project managers and project schedulers of the company to use the P6.0 V7.0 in client server
  • Designing the procedure needs in EPC project as a Coordination procedure, Vendor Project control procedure, Vendor Numbering procedure…
  • Template the schedule of the gas station by more than 90