PLANNER, SARPI, GAS COMPRESSION UNIT
.. Project Supervising : Analyses of progress deviation using Primavera3 and Excel
.. Raise the stat summary and bulletin board for evaluation of activity
.. Project Supervising : Analyses of progress deviation using Primavera3 and Excel
.. Raise the stat summary and bulletin board for evaluation of activity
Worked with one of the major MNC,M/s Daelim Industrial Co. Ltd. with base origin in South Korea employing highly qualified team of around 2500 specialists at Daelim Engineering & Construction, involved in comprehensive range of feasibility studies, project management, engineering, procurement, construction, commissioning & start up, operation & maintenance & project financing.
Worked with VIJAY TANKS & VESSELS LTD., BARODA (An ISO 9001 & ASME ‘U’ Stamp Company) from July 1996 to July 2003. VIJAY TANKS & VESSELS LTD., a 25 Million Dollar company employs more than 200 engineers and is involved in engineering, procurement and construction of storage tanks, pressure vessels, mounded storage facilities (Technical Collaboration with M/s Tissot S.A.France), double wall tanks for cryogenic use, plant product piping jobs and LSTK projects
An engineering and management professional with 15 years experience in project management, specifically in the field of construction and commissioning of pressure vessels and atmospheric storage tanks for Oil and gas storage, with involvement in project management & control, Planning, quality, safety, construction, in the related areas given below :
Controlling and monitoring projec
Worked as a Maintenance Engineer at Indian Oil Corporation Ltd., Mathura Refinery, for the on going Annual Maintenance Contract during the period Jun 1995 to June 1996
An engineering and management professional with 15 years experience in project management, specifically in the field of construction and commissioning of pressure vessels and atmospheric storage tanks for Oil and gas storage, with involvement in project management & control, Planning, quality, safety, construction, in the related areas given below :
.. To prepare baseline schedule.
.. To prepare master, Level 3 & level 4th schedule.
.. To prepare resource histogram of project staff, manpower and plant & equipment.
.. To prepare manpower mobilization plan
.. To Prepare latest forecast plan as per latest forecast quantity.
.. To update schedule (Engineering, Procurement, construction : resources & progress using
the Cost center concept)
.. To prepare Weekly and monthly report,
.. To check the daily report submitted by area planner
In charge of the block 17 Exploitation Planning
.. To collect all relevant information from various departments and services, onshore and
offshore, and to populate the dedicated planning tool.
.. To identify/anticipate all conflicts and clashes between activities (means and meanning);
.. To ensure that Block 17 planning is communicated and updated in time to Division
Planning of the affiliate;
.. To ensure that all information are correct; relevant and with required level of details for the
Early Work Team / Constructibility / Detailed Schedule Preparation /Detail Engineering Support