sennior planner , MAN , reunion island power plant commisionning and extension

START Date
END Date

may 2012 – today

Senior  planning &project control manager

Man diesel turbo

240 mw engine diesel power plant erection and commissioning 300 millions euro project 12 engine EPCM  contract

Oct  2011 april 2012

Sr.Planning Engineer, Mechanical Engineering & Contracting Co. Ali Alghanim Group, (various projects)

START Date
  • Develop program of work (Schedule) with all resource and cost loaded as baseline.
  • Ensure that Subcontractor’s planning services & reporting meets project and business requirements as per the project coordination procedures throughout the duration of the contracts.
  • Produce Schedules for project review for various development options.
  • Develop Presentation Summary schedules as required as reporting.
  • Monitor the progress of work, Manpower, equipment, productivity and subcontractor’s schedule.

Sr.Planning Engineer, Mechanical Engineering & Contracting Co. Ali Alghanim Group, (various projects)

START Date
  • Develop program of work (Schedule) with all resource and cost loaded as baseline.
  • Ensure that Subcontractor’s planning services & reporting meets project and business requirements as per the project coordination procedures throughout the duration of the contracts.
  • Produce Schedules for project review for various development options.
  • Develop Presentation Summary schedules as required as reporting.
  • Monitor the progress of work, Manpower, equipment, productivity and subcontractor’s schedule.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.

Lead Planning Engineer , Laing O 'Rourke, water Treatment Plant

START Date

q  Managing a team of 3 planners

q  Develop a Level 4 Integrated Schedule for Construction Scope of works.  

q  Integrated Engineering, Procurement, Construction & Commissioning Disciplines,

q  Tracking Progress, Weekly Schedule Update, Monitor impact on Critical Path

q  Analyzed the estimates for allocated Budgets to different Work-Packages for the project.