Oil / Gas / Power

David Craig

D
David Craig 👤 Member for 16 years 8 months
First Name
David
Last Name
Craig
Professional Since
Oldest experience
Years Experience
6

Time served electrician turned project planner.

Project planning since July 2010.

Worked in Nuclear, Petrochemical, Oil & Gas, Infrastructure, Oil/Gas Rigs, Commercial and Domestic.

Proficient in the use of Primavera P6, Microsoft Project, Microsoft Excel, Microsoft Word, Microsoft Access & Microsoft Powerpoint.

Ty Nielson

T
Ty Nielson 👤 Member for 18 years 2 months
First Name
Ty
Last Name
Nielson
Professional Since
Oldest experience
Years Experience
37
Telephone Number
13603124329

Project Manager, Superintendent, Scheduler, Layout, Foreman, Tradesman

Vijayakumar N

First Name
Vijayakumar
Last Name
N
Professional Since
Oldest experience
Years Experience
46
Telephone Number
+91 9487149679
Facebook Profile
https://www.facebook.com/vijaykumar.n.779

Position Applied for Planning Engineer

 

Vijayakumar Nachimuthu

Cell No: (+91) 9487149679, 9994619671

Email: [email protected]

Passport No: H8730264, valid up-to 24.02.2021

5/124 Anna Nagar, Covai Road,

Pollachi 642 002

Assistant Planner or Planning Engineer, M/s SHILPI ENGINEERING PVT LTD, Reactor & its Structural Module Reaction 350MT, Manali Refinery, Chennai

START Date
Experience Hours (Planning & Scheduling)
800
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
0

Work Experience (5 Years):

 

Shilpi Engineering Private Limited, Navi Mumbai

 

2016 [From Dec]

Project: Reactor & its Structural Module Reaction 350MT, Manali Refinery, Chennai.

Client  : Chennai Petroleum Corporation Limited

Role     : Planning Engineer

Value  : 3.36 crore

Lead Planning Engineer, Oilserv, UAE, EPC for Summail Gas Processing Facility Client: DNO.EP & Assembly- Design, Manufacture and Supply of Packaged Water Treatment and Disposal Plants- Client: BP,EPC - Bijell-1B EWT Facility Upgrade – MOL. EPC - Bakrman -

START Date
Experience Hours (Planning & Scheduling)
3900
Experience Hours (Cost Management)
1300
Experience Hours (Forensic Analysis)
550

All the Projects Clients are in Iraq - BP, DNO, MOL. • Project Baseline Schedule preparation in Primavera 6.• Preparation of S Curve, Histograms, Budget, and Progress measuring system.• Updating of schedule on a weekly basis in Primavera 6.• Coordinating with the engineering crew to deliver the deliverables on time.• Keeping track of project on a daily basis.• Weekly and monthly reporting which includes cost reporting.• Bi weekly cost reporting.• Alerting the construction team of the ob

Planning Engineer, Pureworld Middle East - Abu Dhabi, Inter Refinery Pipeline – II Client:TAKREER, Oily Water Sump Project - Habshan Facilities - Client:GASCO, Construction of Cathodic Protection of Well Casing - Client: ADCO

START Date
END Date
Experience Hours (Planning & Scheduling)
6700
Experience Hours (Cost Management)
1900
Experience Hours (Forensic Analysis)
850

• Preparation of Planning Package as per agreed Schedule and WBS Structure.• S Curve Preparation.• Preparation of Effective Project Progress Monitoring System.• Weekly, Monthly and Daily Report Preparation for Client and Management.• Review of Project Progress with Project Construction Team so as to notify of any deviation and corrective actionpreparation.• Project Budget and Cash Flow Preparation.• Project Cost Control and Reporting.• Subcontractor Administrat