Planner, Kentz Russia LLC, Sakhalin 1, Odoptu FSP, North Well Site

START Date
END Date


4 years experience in construction on Oil& Gas Production Projects (Primavera P6/ Microsoft Projects software)



1. Developing Master Schedule 

2. Developing Work Execution Schedule

3. Determine Resources for planned works

4. Distribution of Look Ahead’s

5. Developing and maintaining of Equipment Maintenance Schedule

6. Guidance to all work fronts to maintain time line for activities

7. Maintain standards of Planning and comply with Company’s Planning & Scheduling requirements.

Senior Planner, Boland Payeh, Pardis Urea & Ammonia Petrochemical Plant; Zabol Cement Factory; Yazd Power Plant

START Date
END Date

Working as the Planner and Senior Planner in the following projects:



- Salman Farsi Storage Dam

- Assaluye Urea and Ammonia Petrochemical Complex

- Zabol Cement Factory

- Birjan BMI Main Building

- Yazd Power Plant