Project Controls Engineer, Rio Tinto, Gove Sustaining Capex Portfolio
The primary purpose of this role is:
The primary purpose of this role is:
Ensure there was alignment between the various project controls disciplines that included;
Reporting
Scheduling
Cost Magaement
Risk management
Document Control Control
Preparing yearly Capex Budget for approval.
Verification of contracotirs monthly invoices.
Estimating products for drilling & mining businesses across world customers, planning current production processes by using Primavera P6 & Microsoft Project tools. Utilizing PRINCE2 Project Management methodology.
Cooperating with R&D and Customer Service departments.
O’DONNELL GRIFFIN: Senior Project Planner/Asst PM – Brockman 4 Phase 2 Expansion Project (FIFO) – project upwards of AUD$20mm
JOHN HOLLAND MINERALS AND INDUSTRIAL: Project Controls Lead, WA
CALIBRE GLOBAL PTY LTD: Senior Planner – Brockman 4 Phase III FEED/Koodaideri Bid-Tender/Yandi Engineering/Turee Syncline – Projects ranging from AUD$80mm to AUD$500mm.
KALAGADI MANGANESE MINING: Site project planner (September 2010 to June 2011)
ü Developed and managed mining schedule (mining shafts, infrastructure and sinter plant) construction works
ü Pioneered resource allocation and produced costing reports integrated into the schedule
ü Researched and managed risks associated with project delay
ü Coordinated and Managed subcontractor schedules
ü Verified and consolidated mining weekly progress update
ü Developed and generated monthly critical paths
Global cost engineering leader, setting frameworks, processes, procedures, systems for use globally in all businesses