BHP Billiton Lead Planner
Worked as Electrical Planner and then Lead Shutdown Planner
Worked as Electrical Planner and then Lead Shutdown Planner
Preparation of Project Monthly Reports, Cost Estimates and Forecasts, Cash-flow forecasts, progress payment/variation analysis, accurate allocation and maintenance of costs for company asset register, liaison with construction contractors, vendors and other project department groups, contract administration.
Worked as electrical and Project planner
Current Role
CVG Interlumina, Puerto Ordaz Venezuela, 11/1987 87 to 12/1992
Planning and Control Manager Direct Hire Expansion Project reporting to Project Director Consortium CVG- Alussiesse Engineering
• Planing and Control manager for the mega Project ( more than 5000000 mhrs) Two-million ton per year expansion of Alumina refinery. reporting to the Project Director .Project included the installation of new process tanks, heat exchangers, cyclones, conveyor belt, traveling stacker/ reclaimed, barge unloading facility, Materials handling facility with Grinding area.
Current Role
MINING & MECHANICAL HANDLING PLANNING EXPERIENCE - SOUTH AFRICA
1983 Shell Coal South Africa, Coal Mine Development. Approached by Shell to produce a CPN to co-ordinate all aspects of a SA Rand 2M tender for the development of a grass-roots coal mine and its infrastructure.
1978-80 Sasol III Wet Screening and Coal Handling Plant, South Africa. Responsible for development and monitoring of the multi-disciplined detailed engineering design.