Project Control Manager, BEIJING CONSTRUCTION ENGINEERING GROUP CO. LIMITED, KSA, SABIC MEGA HOUSING PROJECT PHASE-III, CONSTRUCTION OF 1280 VILLA PRECAST AND CONVENTIONAL FOR PACKAGE#2, 3,4

Z
zafar khan 👤 Member for 12 years 7 months
START Date

Beijing  Construction Engineering Group Co. Ltd.  Al- Jubail KSA

Project Control Manager

From Oct. 2012 to Continue now

Reporting to: Project Manager

Project : - SABIC MEGA HOUSING PROJECTS – PHASE III HAII JALMUDAH PACKAGE No. 2, 3 & 4

 

Client : - SABIC

 

Key Responsibility Areas:

Mahmoud Abohashem

First Name
Mahmoud
Last Name
Abohashem
Professional Since
Oldest experience
Years Experience
4
Telephone Number
00201003311543
LinkedIn Profile
eg.linkedin.com/pub/mahmoud-abohashem-pmp-psp/39/bb1/765/

Planning and Project Controls Engineer with 5 years professional experience in construction projects management (High Rise Buildings , Power Plants, Industrial Facilities, Embassies), self motivated and believing in continuous development, PMP and PSP certified, next step is preparation of CCP certificate from AACE, still have much to learn and always will be.

Skills:

  • Primavera P6
  • Planning and Scheduling
  • Progress Monitoring
  • Cost Loading and Updating
  • Contracts
  • Time Impact Analysis
  • Attendance Management

Site Engineer, AFRINA Trading and Construction , Jumana Tower-Pearl Qatar-Doha-Qatar

START Date
END Date

• Responsible for supervision finishing works ( Block Works-Plastering-Water Proofing-Ceramic-Painting-Gypsum Board)

• Quantity Surveying of mentioned works for sub-contractors

• Controlling progress of mentioned work activities through daily basis reporting.

• Planning of work activities on a weekly basis plan.

Project Controls Engineer, ARCONS, Alkhalij Power Plant - Sirt Libya

START Date
END Date

• Reviewing and studying contract agreement.

• Preparation of Method Statement for Erection of steel structure and tanks.

• Preparation of master and detailed project schedule (Primavera P6).

• Updating and follow up project schedule.

• Preparation of Daily, Weekly & Monthly Progress Reports.

• Preparation and follow up Material Control System.

• Control and follow up of monthly payments.

• Coordination and control of all incoming and outgoing e-mails and letters from and to the client.

PLANNING COORDINATOR, Mancon Consutlancy and Project Management , Mantrac Takoradi New Facility-Ghana

START Date
END Date

* Preparing master and detailed time schedule (using primavera P6 and MS Project).

* Coordination with design team to prepare tender package

* Evaluation and awarding of contractors.

* Preparation of contract agreements complying with FIDIC standards.

* Preparation of projects budget.

* Following up construction phase (time and cost).

* Coordination with different project parties (emails - meetings).

* Document controlling (project documents - historical data - lessons learned)

Craig Stevens

First Name
Craig
Last Name
Stevens
Professional Since
Oldest experience
Years Experience
4
Telephone Number
07731145079

Senior Planner at Amco.

 

Proficient in P6, MS Project, Excel.