Civil / Building / E&M

ANALYST / PLANNING ENGINEER, Gammon Construction (HK) Ltd, science park

START Date
END Date
Experience Hours (Planning & Scheduling)
400
Experience Hours (Cost Management)
100
Experience Hours (Forensic Analysis)
100

Prepare Master Construction Programme

Assessment of labour requirement

Establish plant/finishing schedules

Generate Monitoring tools such as S curve, charts and tables

Organize adhoc presenation for task force meetings

Prepare monthly / Weekly Reports

Review programmes, monitoring schedule of sub contractors

Update master construction programme

Create Site layout plan/ 5 week look ahead / 3months rolling programme

Generate a coordination programme for interfacing works

Scheduling Manager, Q&D Construction, Univ of Nevada Reno, Mathewson-IGT Knowledge Center

START Date
END Date
Experience Hours (Planning & Scheduling)
50

A $70 million state-of-the-art project combining the best of traditional university library resources with innovative digital and multimedia technologies.  The project included a 163-seat auditorium, a dynamic media lab, a Basque studies library, and an automated book retrieval system housed within a 295,000 SF classic brick building.

Scheduling Manager, Turner Construction, Caltrans Headquarters

START Date
END Date
Experience Hours (Planning & Scheduling)
50

A $60 million, 205,000 SF headquarters building comprising design and engineering studios for 758 employees, a 200-seat auditorium, public service counters, teleconferencing facilities and a cafeteria. 

Scheduling Manager, Swinerton Builders / Q&D Construction JV, Ritz Carlton

START Date
END Date
Experience Hours (Planning & Scheduling)
50

A $250 million Hotel built at 7,000 feet elevation.  This project required schedule updates on a weekly basis for over 3 years.  The procurement schedule was very detailed and instrumental in coordinating material deliveries between the Owner, their Design Team and the General Contractor.

Scheduling Manager, Turner Construction, Migration from Primavera P3 and SureTrak

START Date
END Date
Experience Hours (Planning & Scheduling)
50

OnTrack helped the Turner Northern California business units transfer all of their project schedule to the new P6 Enterprise Project System.  Because of a highly successful business partnership, OnTrack worked with Turner to manage this critical conversion which laid the groundwork for the company to perform primary scheduling services for numerous Turner projects throughout Northern California.

Scheduling Manager, Rudolph & Sletten, Red Hawk Indian Casino

START Date
END Date
Experience Hours (Planning & Scheduling)
50

A $198 million Casino Development built by Rudolph & Sletten Construction required excellent interview techniques and creative methods to build a well-coded 5,000 activity baseline schedule. The key to success was the activity and area.

Scheduling Manager, First Solar / M+W Group, First Solar Thin Film Manufacturing Facility

START Date
END Date
Experience Hours (Planning & Scheduling)
50

OnTrack provided Lead Scheduler services on this project in Mesa, AZ. Upon joining the project, OnTrack was tasked with rebuilding the schedule WBS, validating activities, and clarifying the project controls reporting process. After successfully establishing a new project baseline schedule, OnTrack conducted weekly scheduling meetings for both the CM and subcontractors, and developed “What-If” schedules to analyze workaround scenarios on this fast track project.

Scheduling Manager, M+W Group, Intel CH8 Packaging Research & Development Facility

START Date
END Date
Experience Hours (Planning & Scheduling)
50

OnTrack was a by name request to join the M+W Group team responsible for the construction of the $300M Intel CH8 facility in Chandler, AZ.