Civil / Building / E&M

Estimation & Cost Engineer; Project Control Engineer, Constructora Pinto, Civil and Mechanical works

START Date
END Date
Experience Hours (Planning & Scheduling)
250
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
100

Performed daily monitoring of Site activities, highlighted delays and advised recovery actions; prepared project expenditure and progress reports; generated and updated contract resourcing plans

Civil Chief Inspector , Alcaldia de Puerto Cabello, Civil and Mechanical works (various)

START Date
END Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
100

Performed civil works inspections; reviewed and approved construction invoices, supervised and managed inspectors and subcontractors

Controls and Budgeting Senior Engineer, Alcaldia de Puerto Cabello, Civil and Mechanical works (various)

START Date
END Date
Experience Hours (Planning & Scheduling)
450
Experience Hours (Cost Management)
450
Experience Hours (Forensic Analysis)
200

Leader of the Division with a primary role for development and implementing project cost control systems to manage, control and forecast projects costs as well as to provide to Municipal Engineering Manager the status/progress of all the projects .Duties included:

Offsite Project Execution Coordinator, Kayson, 10,000 unit-housing project

START Date
END Date
Experience Hours (Planning & Scheduling)
50
Experience Hours (Cost Management)
50
Experience Hours (Forensic Analysis)
50

Main officer for 10,000-Unit housing Project (Offsite works) responsible of organizing and maintaining the best integration between scheduling, cost control and Risk Management functions. Duties included:

florangel millan

First Name
florangel
Last Name
millan
Professional Since
Oldest experience
Years Experience
10
LinkedIn Profile
ve.linkedin.com/pub/florangel-millan/6a/a2b/3b/

OBJECTIVE 

To act in the planning, estimate and control of the projects, systems and procedures of different processes. To plan, to coordinate and to direct the activities that are carried out in the companies in effective form, with the purpose of eliminating interruptions in the process and using unnecessary manpower and material. Being able to work  in the following departments:

Ø    Contract Administrator

Senior Planning Engineer, Al Muhaidib Contracting Comapny, Taibah Hospital Project Madnia - KSA

START Date
Experience Hours (Planning & Scheduling)
850
Experience Hours (Cost Management)
950
Experience Hours (Forensic Analysis)
150

Planning, Scheduling, Tracking, Forecasting, Reporting, Claims Handling, contract handling, technical support. 

Project Coordinator and Quantity Surveyor , M.N Abu Eid Establishment, Commercial, administration and housing facilities projects

START Date
END Date
Experience Hours (Cost Management)
6500

·         Preparing a tender and contract documents, including bill of quantities BOQ

·         Undertaking detailed take offs in the format to be use within interim or payment applications and Variations

·         Prepared the materials schedule for approval and request for quotation (RFQ).

·         Monitored all materials requested are received and follow up ahead the others to avoid delays.

Assistant Manager - Project Management, DURACELL, IMPLEMENTATION OF CELL MANUFACTURING ASSMBLY LINES

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
800

In charge of supervising the adaptative design and erecting work of several cell manufacturing assembly lines in the plat facilities, including tolls and machines constructed loccally using basic design from USA and Netherlands plants.

In charge of mechanical and electrical maintenance supervising people working in shift hours