Deputy Planning Manager, Shapoorji Pallonji & Co Limited, Maruti-Suzuki India Limited- Automobile Factory construction

START Date
Experience Hours (Planning & Scheduling)
2450
Experience Hours (Cost Management)
1350

I am working currently as a Deputy Planning Manager in Shapoorji Pallonji Construction Private Limited on an Industrial Project in North Gujarat, India.

The Project Specifics.

Project value-Rs. 503 crs

Project duration - 29th January'15- till date.

Project Brief- Construction of Maruti-Suzuki Manufacturing Plant. I look after 

1) Press Shop

2) Weld Shop

3) Infrastructure- Roads, Storm water drains, Sewerage lines.

 

I look after the Project planning, scheduling, tracking, cost monitoring, project co-ordination, budgeting.

Project Control and Planning Engineer‎, Tebodin, various projects in Netherlands, UK, Russia

START Date
END Date
Experience Hours (Planning & Scheduling)
20800
Experience Hours (Cost Management)
9000

Worked for Tebodin from 1991 up to 2005 as a Project/Control Planning Engineer. Was involved with a diversity of projects in various industries from the home office(s), but also seconded at clients in various locations (Netherlands, Russia)

Chi Kwan Fong

First Name
Chi Kwan
Last Name
Fong
Professional Since
Oldest experience
Years Experience
14
Telephone Number
9098694062

Project Management and construction Management

Senior Project Manager, University of California Riverside, buildings

START Date
END Date
Experience Hours (Planning & Scheduling)
1350
Experience Hours (Cost Management)
1300
Experience Hours (Forensic Analysis)
100

project management, design management and construction management, contract management, and sustainability management

Senior Project Manager, University of California Riverside, buildings

START Date
END Date
Experience Hours (Planning & Scheduling)
1350
Experience Hours (Cost Management)
1300
Experience Hours (Forensic Analysis)
100

project management, design management and construction management, contract management, and sustainability management

Project Planner, M.A. Khrafafi and Sons, Kuwait, BAYAN PALACE, PHASE II PROJECT, KUWAIT

START Date
END Date

BAYAN PALACE, PHASE II PROJECT, KUWAIT. Project is spread over in Bayan area, Kuwait featuring worldclass

interior finishes which also included large area of hard and soft landscaping.

As a Planning Engineer – Responsibilities included Project Planning & Scheduling, Variation evaluation,

Baseline and change monitoring, Review of Payment Applications, Time Extension analysis, Progress reports,

and Progress follow‐ups, cash flow forecast, coordinating subcontractors programme, writing letters

Planning Engineer, Galfar Engg and Contracting LLC, Oman, Al-Araimi Towers, Oman

START Date
END Date

AL‐ ARAIMI TOWERS, Al Khuwair, OMAN :

Planning Engineer ‐ Responsibilities included scheduling, Planning and monitoring of manpower, materials and cash flow for ongoing projects, generating weekly / fortnightly progress reports for Management and Consultants.

CRUDE OIL STABILIZATION PROJECT FOR P.D.O, OMAN

Scheduling, Planning and monitoring of manpower, materials and cash flow for ongoing projects, generating weekly / fortnightly progress reports for Management and Consultants.

Senior Planner / Senior Planning Engineer, KEO INTERNATIONAL CONSULTANTS, Al Mohalab Centre, Kuwait

START Date
END Date

During my time as Sr. Planning Engineer for the Al Mohalab Centre, Kuwait interfacing with clients, design

consultants, and Contractors. My responsibility included Project Planning & Scheduling, Variation evaluation,

Review of Payment Applications, Time Extension analysis, Progress reports, and Progress follow‐ups,

preparing and updating risk register, progress presentation to client.

This commercial complex has a unique boat shape and sleek, ultra‐modern design. The multistoried building

Senior Planner / Senior Planning Engineer, KEO INTERNATIONAL CONSULTANTS, The College of The North Atlantic campus (COT Qatar)

START Date
END Date

During my time as Sr. Planning Engineer for the College of Technology project from concept design phase

thru project construction close out phase. Responsibility included managing programmes from designer and

construction contractors, tender process for all bid packages, analyzing and generating various reports,

contractors claim analysis, maintaining risk register, tracking long lead items / conducting procurement

meeting, and updating risk register. This project was initiated by the Qatar Government, which is now known

as CNA‐Q campus.