GLOSERVE Planning Consulting – Freelance Planner

 

Worked as part of GLOSERVE, being seconded to the following companies

 

  • RG Carter– University of East Anglia Student Accommodation and a Hotel in Cambridge worth circa £45m - JCT D&B - ASTA.
  • Greendale Construction- Covering maternity leave on a GP surgery - £5m refurbishment project. Including building a new wing - JCT D&B - ASTA.

 

Duties included: -

Construction Project Planner , Bougyues, -High Ends Residential Building Project

START Date
END Date
Experience Hours (Planning & Scheduling)
6600
Experience Hours (Cost Management)
550

 

This was more of office-based overseeing 4 live sites and providing monthly updates and drop lines. Also supporting site when required. These were both NEC & JCT forms of contract and projects included: -

 

  • Lady Margaret Student Accommodation - £12m
  • Church Crookham Residential Home in Guildford new build JCT - £10m
  • Havelock Mix-use New built Houses Phase 1- £30m
  • Fountain Close – new build residential mixed-use site - £25m

 

Roles and responsibilities included;

Pre-Construction/Construction Project Planner , ISG plc, & Various commercial

START Date
END Date
Experience Hours (Planning & Scheduling)
18300
Experience Hours (Cost Management)
700

 

 

 

 

 

 

ISG PLC – Planner

 

. During this time, projects have included: -

 

Amazon Darlington (£120M);

Construction of a new Fulfilment Centre including warehouse, office and welfare space, S38 works, 278 works and all other associated external works.

 

Grafton Shopping Centre (£40M);

# Senior planning engineer #Joint Venture # Senior planning engineer, Clugston Construction via Edge Freelance, WASTE TO ENERGY POWER GENERATION PLANT

START Date
END Date
Experience Hours (Planning & Scheduling)
6600
Experience Hours (Cost Management)
3650
Experience Hours (Forensic Analysis)
2500

Construction of Energy Recovery Facilities, the works  include  the construction of  all infrastructure,buildings, roads, Building services,offices,workshops,process plant, Turbine, landscaping, security fencing and all associated amenities & facilities. Role and responsibilities included: • Working on live projects to provide scheduling and planning support to project managers and stakeholder• Liaising with sub-contractor to develop

Abhishek Ram

First Name
Abhishek
Last Name
Ram
Professional Since
Oldest experience
Years Experience
8
LinkedIn Profile
https://www.linkedin.com/in/abhishek-ram-pmp%C2%AE-ab450345/

/ Construction Project Planner / Senior Planner, Simplex Infrastructures Limited, Various 2/4/6 laning NationalhIGHWAYS pROJECTS

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
250
  • Preparation of fully resource and expense loaded Baseline Construction programme in Microsoft Project 2010 with 15000+ activities.
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Prepared & presented monthly reports to top management in monthly project meetings.
  • Prepared resource optimization report.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Preparation of Delay tables, Productivit

/ Construction Project Planner / Senior Planner, Larsen & Toubro (L & T) Limited, 000ft2 Office Building

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
500
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Evaluates the impact of changes on cost, schedule, operations and scope documents.
  • Participate in meetings with Project Managers and provide schedule related input.
  • Prepared & developed L2 & 3 Level Baseline construction programme in P6.2 & updating the same on weekly basis.
  • Record and

#planning #seniorplanner #planningengineer #construction #build #majorprojects, Al Turki Enterprises - Oman, Ras Al Hamra Development Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
250
Experience Hours (Forensic Analysis)
250
  • Preparation, submission & obtaining approval for fully resource & cost loaded schedule using Primavera P6.7
  • Core team member for implementation of SAP – PS module for project planning & tracking.
  • Preparation of daily, weekly & monthly reports in strict compliance with procedure implemented by Halcrow ME as a part of project controls process.
  • Played an important role in developing & implementation of salary structure for manpower based on productivity delivered.
  • Productivity analysis.
  • Preparing two/four week look ahead.

Lead Planner, Jacobs UK, Horizon Nuclear Power

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
4000

Chair periodic schedule management meetings to coordinate, understand and manage project interdependencies.Ensure a lean and flexible approach to schedule management is maintained to meet the changing demands of a development project.