Lead Schedule Manager, Bravo Consult Limited, Manchester Airport Transformation Programme

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Forensic Analysis)
1000

Schedule management lead, working with Arcadis, on the Manchester Airport Transformation Programme. Successfully led a team of 5 planners in developing, managing and maintaining the schedule for the £1.00bn transformation of Manchester Airport: a 15 year programme of work which will increase the airport's passenger and aircraft capacity, while improving the customer and stakeholder experience.

Nikhil Bellur

First Name
Nikhil
Last Name
Bellur
Professional Since
Oldest experience
Years Experience
23
Telephone Number
+447983018910
LinkedIn Profile
in/ngbellur
Facebook Profile
bravoconsult?ref=hl&ref_type=bookmark
Twitter Profile
PlanWorkSucceed

Adam Buckingham

First Name
Adam
Last Name
Buckingham
Professional Since
Oldest experience
Years Experience
5
Guild Accreditation
GPC Member

A Project Planner who joined Faithful + Gould in May 2016, currently working on the Q6 Heathrow Asset Management Programme and Heathrow Expansion

Previously spent 3.5 years working for an EPC Contractor, KBR within the Oil and Gas industry. This included a 2 year Project Controls Graduate Training Scheme incorporating rotations in Planning & Scheduling, Cost Control, Estimating and Change Management.

Skills include:

Design Engineer, Marshall Aerospace, C-130H Deeper Maintenance Programme

M
Martin Dunn 👤 Member for 11 years 2 months
START Date
END Date
Experience Hours (Planning & Scheduling)
600

Design Engineer and Project Manager for various aircraft modification tasks. Including secondment to Australia to undertake support for C-130H deeper maintenance programme.

Professor of Project Management - Trainer, SKEMA Business School, DBA project

START Date
Experience Hours (Planning & Scheduling)
400
Experience Hours (Cost Management)
400
Experience Hours (Forensic Analysis)
0

Professor of project management at vaious univeristies, currently at SKEMA Business School. Responsible for managingm directing and update Masters and Doctaoral programmes in project, programme and portfolio management.

Project Planner, HETCo , Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
2000

Development of the master schedule from the interactive planning stage, responsible for setting up the fully resourced and cost loaded programme and progress monitoring using the Earned Value Analysis. Primavera post office was used to get updates from the project team.

Senior Business Analyst; Project Controls developer, OST, FAA NextGen

START Date
END Date
Experience Hours (Planning & Scheduling)
600
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
150

Senior business analyst for FAA’s NextGen P6 Enterprise development

§  Produced Resource elements scope and deliverables

§  Provided development analysis for schedule development sessions

§  Analyzed agency’s approach to R&D for P6 structural mechanisms

§  Developed schedule models, coding structures, resource profiles and procedures

Project Schedule Engineer, Quality Planning Solutions/Turner Construction Company, Miami Intermodal Center, Miami International Airport

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
100

Schedule engineer for $300M MIC MIA, $50M MIC Station projects; P3 3.0, Digger

§  13,000 activity as-built schedule updated in weekly database copy,  2 sub-projects

§  Narrative and CPM analysis weekly and monthly submittals

§  Weekly owner schedule review meetings

§  ‘Last Planner’ (Lean Construction certified) & ‘Pull meetings’ with subs