Project Management Issues Discussion

Description

Talking about Project Management Topics

Container
No

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Omission

Dear All,

Would like to clarify the omission of the scope of work in the contract BQ, material has been procure and the work has been carried out however in the middle of the project schedule the client cancelled the design for the particular work and omit in the contract BQ and doesn't allowed to claim to material purchase and halfway work done, any advise please.

Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Supervision

Dear All,

Need your expertise, Reference to the contract we have carry out additional work which is not in the original scope of work and that involve supervision of work, we have upt up the claim for the supervisor and engineer to supervise these extra work which is not in the original scope of work, however the client/main contractor doesn't allowed to claim the supervision work.

Any advise please...

Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

What is the DIPP? (Warning! Some wonky stuff)

That’s the title of my new article, just up at my blog.



One of the readers of my blog posted a question in the Comments with respect to a metric I had mentioned in passing:



“DIPP tracking. What is it and where can I learn more about it?”

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Why Do We Plan Projects?

Motivated by a discussion on a LinkedIn project management group, I just posted a new blog “Why Do We Plan Projects?” It makes the case that projects must be planned using such flexible techniques as work breakdown structures, value breakdown structures, critical path analysis, activity-based resource assignments, etc. NOT because we know what is going to happen, but because we don’t! And that such a plan becomes most valuable when variances demand a change in plan.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Estimating the Cost of Time When Ain’t Nobody Told Ya!

I just published a new blog post “Estimating the Cost of Time When Ain’t Nobody Told Ya!” at the Total Project Control  website.

This new blog shows how, given only budget and “deadline” instructions, a project manager can do some back-of-the-envelope calculations to generate conservative estimates about the cost of time.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Time Is a Cost Even When Nobody Says How Much

I just published a new blog post “Time Is a Cost Even When Nobody Says How Much” at the Total Project Control  website.  The new blog explains to that even when the sponsor/customer doesn’t recognize the value/cost of time and/or doesn’t know how to incorporate it in a contract or charter, this information is still of particular value to the project manager.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

New blog post “Project Managers Should Revel in Time Analysis!” is just up at the Total Project Control website

The new blog explains to whom the value of time on a project is most important, and who therefore should ensure this metric is available and used. It also explains why this information is so important for project managers whose skill in time management can combine with such data to demonstrate and quantify the value they add to a project.

You can find the article here.

Fraternally in project management,

Steve the Bajan

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts