Hi All,

I am lookingfor advice on software. Currently working on Projects within Pharma industry, we have a Roadmap developed in Excel showing all the projects between 2018 and 2023 (ususlly 5yr rolling calendar). This roadmap has all the major highlevel milestones of the project such as C&Q completion, engineering runs, PV batches, regulatory submissions and approvals.

As we have quite a few (approx 40 projects) on this roadmap, so is looking very busy as I often need to include in prenstations for senior site & corporate mangament.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Cost Loading a Schedule - Input From ?

Hello Everyone,

Just understand where the Cost of each activity would come from if you have to Cost Load a schedule.

The BOQ of a Project would have a lumpsum quantity say for example,

Concrete = 250 Cu M X 350$ / Cu M = 87,500 $.

And in schedule we have activity say,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Weekly Report Dilemma

D
D Artagnan 👤 Member for 17 years 8 months

My new contractor's planners refuse to submit: (these are all stipulated in the contract)

1. Recovery Programme

2. Substantation to Claimed Progress in the weekly reports

3. Procurement tracking system

4. KPIs of the planned and actual works

5. Any of my request to validate their claims (letters, inspection data, approval letters)

 

I have written a letter already and it's still being ignored. 

 

What's your recommendation?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Resource Loading

Hi anyone can help me regarding the subject matter.

I got the xer.file (P6) from our subcontractor with resource loading. however, when I importing the s/c schedule to my P6 the resource loading does not match on his resources. What i'm saying is he has a foreman, mason, carpenter but on my schedule (importing from his xer.file) it doesnt show its different resource is loading.

can anyone advise me how to do this? by the way i'm using P6 version 16.1.

Thanks,

chris

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

change order and reflection in baseline

A
Ahmet Tuter 👤 Member for 13 years 4 months

All change order modify the baseline in some way, such as cost, scope or time. but we do not create a new baseline everytime.

how do we reflect this change order which only modifies part of the basline, in the baseline?

for example, lets say we are building a house, and a change order added a 10 meter wall. we add an activity or activities for building that wall, put in its durations resources, money into it ... and when we do earned value calculations, how does it work for this, for something that did not exist before? This is my question I guess

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Summary vs High Level Activity

A
Ahmet Tuter 👤 Member for 13 years 4 months

I know that a summary activity includes all activities below it and it's everything is calculated automatically according to activities below it.

I also know what high level means.

But I am confused if we should call a summary activity also a high level activity or they are different? What is a summary activity vs a high level activity? What differences are there between them?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Error while exporting project in excel format from p56

S
sanam negi 👤 Member for 13 years 9 months

Hi guys,

 

Need some help regarding the error while exporting the file in excel format from Primavera P6

This error came recently, the error states

 

Export failed. Unexpected error from external database driver (1)Please contact your administrator to correct the problem.  Please advise thankssanam

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts