Alternatives to lags and dummy activities
I haven't seen a good answer to this in the general forum and would really like to know the accepted theory or best practice.
Example the engineering specification for a piece of equipment is available in M2, lets say it happens to be one of the first items to be designed. The procurement process means a purchase can be made in M4. The lead time is 4 months and so it will be available for delivery to site at M8. I only need to install that item in M16.