Developing schedules of detailed engineering phase for oil & gas

R
Raul Santos 👤 Member for 16 years 8 months

Hi everyone,

I would like to ask the experienced guys developing plans and schedules for oil & gas plants about a brief description of each of the disciplines involved (process, piping, mechanical, civil, eletrical, instrumentation & controls)

1. What are the major deliverables produced on each discipline

2. Most important relationships among these deliverables (which comes first, which follows what, etc.)

3. The interface with procurement and construction

4.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Changing the Late Finish Every Week

D
Dura Cell 👤 Member for 15 years 6 months

Dear Planning Planet,

I update our construction programme every week. Because of our poor performance on site the late finish was resulted to be sooner than the early fiinish. My story is when i made a 1 week look-ahead schedule the late finish date is impossible for the actiivity to finish as it gives only a remaining of 2 days for 1 acitivity to be finish. This 2 days is really impossible as per actual performance on site. Now, the project manager want me to move the late finish. I told them this happened because we are delayed. Project Manager want me to adjust the schedule.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Resourse assignments in P6 Ver 7

Hi,

I am a new user of P6 version 7. I want to prepare the program with resourses on it. I am not sure what I am doing is correct or not but I am explaining here to you all (Expert & well experienced Planners) for your comments:

I create a material resourse with the estimated production rate of units/day and assign that to the activity. The activity duration type I keep is "Fixed Units/time". Then I give budgeted quantity so the durations are derived from that.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Resourse assignments in P6 Ver 7

Hi,

I am a new user of P6 version 7. I want to prepare the program with resourses on it. I am not sure what I am doing is correct or not but I am explaining here to you all (Expert & well experienced Planners) for your comments:

I create a material resourse with the estimated production rate of units/day and assign that to the activity. The activity duration type I keep is "Fixed Units/time". Then I give budgeted quantity so the durations are derived from that.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

DRAG of Critical Path

Hi Mr. Stephen Devaux, Mr. Rafael Davila and Mr. Mike Testro

I read the “Critical path Quiz” posted on the PP on Wed, 2011-07-20 16:05 by Mr. Stephen Devaux. It was really a valuable discussion for new planners like me. I saved that in (copy past) in MS Word and studying that and calculated manually and that was correct.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

WBS Files for Government Acquisition Programs - Useful Templates

Hi Guys,



Here are some free WBS templates that you can download for all the Government Acquisition Programs http://bit.ly/zKlU0Y



They are categorized by program type and are in CSV format so you can easily import them into most Project Management and Earned Value Management tools.



I hope you find them useful.



Emily

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Research topic related to planning / scheduling

Hi all,

I am working as lead planner and doing Masters in Project Management. I am looking for some good research topic for my degree, I am just wondering if somone can help find a research topic related to planning / scheduling.

Thanks

Tariq 

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts