Microsoft Project 2013 and the Look Ahead Filter
Here's a great tip on how to create a Look Ahead Filter in Microsoft Project http://ow.ly/wLBo300pa1D
Questions & answers for MS Project software
Here's a great tip on how to create a Look Ahead Filter in Microsoft Project http://ow.ly/wLBo300pa1D
Hi Planners,
How to change currency from dollar to another currency in MS Project 2013?
Best,
Moutaz
Here a great tip on how to use curtains in Microsoft Project to show what work is being done within a Sprint http://ow.ly/4n4SOv
Hi,
Not been able to find an answer to this on the forum, so here goes.
I have a detail schedule that is using groups to set up a Level 0 schedule. There are 7 phases, with each phase containing tasks for four elements (Design, Approvals, Construction, Handover/Acceptance) of the project.
You may find this article helpful: Project Server vs Project Online vs On-Premise vs Project Lite vs PPM vs EPM
Dear All,
While I am trying to change FONT and BACKROUND colour on task or subtasks somehow prevous changed tasks return to origianl colour (black and white) on MS project file. Even when I select 10 task and sub tasks for colour changing some of them stay as black and white.
Your help and support appreciated.
Thanks a lot in advance
Good day Dear Ladies/Gents,
It is big pleasure for me to join this forum.
I am beginner on MS Project and need your advise on how to set up password for MS Project file. So only I (or person knows password) can modify file and rest personnel who has access to this file can open it as read only.
Thanks a lot in advance
Kindly
Leverage the power of the Gantt chart to analyze the impact of task constraints on the schedule http://ow.ly/10DnVU
I have a flag that is set to yes and would like to display in a text field the word contractor but am having problems setting up the formula. Can anyone help?
Dear All,
I am working with MS Project 2010. My calender is 24hr working 7 days a week.
I need to show a column which highlights the planned % complete for a given status date.
This is so we can present to our client (for example) - we should be 40% complete through today but we are only 30% because of XXXX
I am also using an S Curve based on cumulative vs actual manhours.
My plan has been baselined. I have tried a few formulas online but after 6hrs today I am struggling to get one that works!
Can anyone help?
Very much appreciated!