DCMA 14

How to show Baseline Execution Index (BEI) in Microsoft Project

The Defense Contract Management Agency (DCMA) 14-Point Assessment is a set of metrics used to evaluate the quality of a project schedule to ensure that the schedule is fit for purpose. And one of the 14 metrics is the Baseline Execution Index (BEI) which is an indication of how a schedule is performing against a set baseline and the video below explains how to set-up a Microsoft Project schedule to display BEI.