PROJECT NAME: CONSTRUCTION OF 4 STAR 29 STOREY SOUTHERN SUN HOTEL AT MINA ROAD, ABU DHABI, UAE.
EMPLOYER: CHINA STATE CONSTRCUTION ENGIEERING CORPORATION (CSCEC), MIDDLE EAST, DUBAI, UAE.
CONSULTANT: AEDAS LLC
PROJECT MANAGERS : CUMMING INTERNATIONAL
JOB DESCRIPTION: I HAVE PERFORMED INDEPENDENTLY AS A SENIOR PLANNEER AND HAVE BEEN SOLELY RESPONIBLE FOR ALL PLANNING AND PROJECT CONTROL TASKS CONDUCTED DURING THE COURSE OF THE PROJECT.
IMPLEMENTED AND MANAGED MASTER SCHEDULE FOR THE PROJECT CONTAINING ALMOST 3000 ACTIVITIES.
Prepare construction program of works related to Civil /Structural/ID /MEP / Firefighting & Fire alarm/ELV discipline wise detailed man-hours , cash flow, dashboards, s-curves using Primavera P6 & MS Project and ensure that the Project Plan reflects the project scope and is fully resourced and cost loaded in reference to the BOQ and Engineering drawings issued for site construction.
Prepare Revised Program for the remaining works and recovery program.
Check and Update program of works as required for the project through close out, integrating contractor and prog
Department: Project Planning & Monitoring at Corporate Office
Role & Responsibility: Lead Planner at Corporate office and handled multiple Projects at various locations of U.A.E with help of associate team members
Projects handled - Hilton Hotel & Resorts, G+9 Commercial Building at Business Park, G+10 Staff Accommodation Building at Industrial Park, Pre-cast Factory at Technology Park, District Cooling Plant at Business Park, Staff & Labour Accommodation buildings, Ware Houses, Commercial & Residential buildings & Luxury Villas and actively involved in tendering stage Projects
Consul