Senior Delay Consultant, Trett Consulting, Multi Projects
Casino Fit Out - Delay Analysis (Time Impact Analysis) in support of the Contractors EoT claim and subsequent adjudication.
Shopping Centre Demolition - Delay Analysis (As Planned v as Built) in support of EoT and delay and disruption claims.
Gas Processing Plant - Delay Analysis (As Planned v As Built) in support of EoT and delay and disruption claim.
Claims Consultant, Trett Consulting, Various Projects
Provision of contractual advice in the preparation and defence of claims to be negotiated, adjudicated, arbitrated or litigated, including a loss and expense claim for a sub-contractor, an overview of potential claims and defences available to an employer and general commercial pre-contract advice to developers, employers, contractors and sub-contractors.
Engaged and managed external legal advisers including counsel, on behalf of clients.
Claims Consultant, Trett Consulting, Coke-Cola Concentrate Plant in Ireland
Preparation of Extension of Time Claims and associated costs for Contractor on a Coke-Cola Concentrate Plant in Ireland
Forensic claims consultant & contracts specialist, Trett Consulting, Construction of 4 Container Ship Hulls
Valuation of Work performed by Shipbuilding company in Poland for Turkish Client