Planning Engineer Manager, TR Oman (Tecnicas Reunidas), Saih Rawl Gas Compression and Power Generation Project.
START Date
END Date
- Created the overall master plan, level 5; commissioning schedule; installation and modification control room; logic integration test plan and other relevant documents using Primavera, MS Projects and other tools.
- Generated work reports (daily, weekly, monthly) including information on critical activities and critical path.
- Chaired all planning meetings with management and construction site staff, coordinated site activities shown in Primavera P3, MS Projects and other tools.
- Focused on critical path tasks and identified problems during project