Scheduling Manager, Swinerton Builders / Q&D Construction JV, Ritz Carlton

START Date
END Date
Experience Hours (Planning & Scheduling)
50

A $250 million Hotel built at 7,000 feet elevation.  This project required schedule updates on a weekly basis for over 3 years.  The procurement schedule was very detailed and instrumental in coordinating material deliveries between the Owner, their Design Team and the General Contractor.