Principle Projects Planner, Sundance Resources, Mbalam-Nabela Iron Ore Project
START Date
END Date
Experience Hours (Planning & Scheduling)
5900
Experience Hours (Cost Management)
1650
Experience Hours (Forensic Analysis)
500
Mbalam-Nabela Iron Ore Project– US$6 Billion 35 Million tonnes per annum Iron Ore Project in Cameroon and Congo (West Africa) consisting of 600km Rail, Iron Ore process Plant, Port Material Handling and Ship loading facility, Airport & Accommodation facilities
Principal Projects Planner (7 months full time, then consulting role as required)6/2010to 10/2014