Area Planning Engineer, SOJV - Taisei Corp - TAV, Airport (Doha), (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building

START Date

 

v  Prepare Tender Preliminary schedule including Project Codes, Activity Codes and WBS Codes

v  Prepare detail Baseline Construction Schedule incorporating all the aspects of works from Engineering, Procurement, Mobilization, Construction, Fabrication, Installation and Turn-over

v  Prepare Histograms, S‐Curves, Cost/ Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.

Area Planning Engineer, SOJV - Taisei Corp - TAV, Airport (Doha), (2) 3B+G+14 Stories+ Swimming Pool (Office & Residential) Building

START Date

 

v  Prepare Tender Preliminary schedule including Project Codes, Activity Codes and WBS Codes

v  Prepare detail Baseline Construction Schedule incorporating all the aspects of works from Engineering, Procurement, Mobilization, Construction, Fabrication, Installation and Turn-over

v  Prepare Histograms, S‐Curves, Cost/ Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.

Sanju Sunny

First Name
Sanju
Last Name
Sunny
Professional Since
Oldest experience
Years Experience
42
Telephone Number
+97455285673

Document Controller, SOJV - Taisei Corp - TAV, New Doha International Airport project (value of 15 billion QR); Managed by Overseas Bechtel

START Date

v  Preparation of Transmittals for the submission of subcontractors.

v  Preparation of Transmittals for Internal Distribution.

v  Updating Various Log sheets.

v  Receiving subcon Letters.

v  Filing Invoices, Incoming and Outgoing letters, Transmittals, to the appropriate files.

v  Labelling of each folders.

Planner/Senior Planner/ Claims Planner, SOJV - Taisei Corp - TAV, New Doha International Airport (NDIA project)

R
Robin Reyes 👤 Member for 19 years 9 months
START Date

Baseline preparation, progress monitoring and proress reports as requirement of project Engineer.

Time Impact Analysis as a results of various instruction of the Engineer for the Contractors claim for time extension